|
Case
01-F-1276 TransGas
Energy Systems, LLC Task Force Comments on TGE Preliminary Scoping
Statement and Proposed Stipulations, with TransGas Energy Responses INTRODUCTION Pursuant to Article X of the Public
Service Law and implementing regulations, the Community Board One and the
Greenpoint Williamsburg Waterfront Task Force[1],
a coalition of 40 Brooklyn community organizations, (hereinafter
collectively “Task Force”), respectfully submit the following comments
on the Preliminary Scoping Statement (“PSS”) of the proposed 1,100
megawatt (Mw) TransGas Energy generation project for the East River
waterfront. The filing of the PSS triggers the duty
on the part of the Applicant to initiate formal consultation with involved
agencies and the public. PSL
§163 (3),(4). The purpose of the Task Force comments submitted herein is
to put the Applicant and involved agencies on notice as to what the
community regards as the fundamental gaps in TransGas Energy’s
identification of, and program to assess the economic, environmental, and
social issues that arise in connection with the project.
These central issues must be fairly, objectively, and
comprehensively addressed in determining whether the project is in the
public interest. PSL § 168 (2)(e). For the reasons set forth in detail
below, TransGas Energy’s PSS is deeply flawed.
Indeed, the PSS is replete with self-serving, inaccurate,
incomplete and misleading narrative regarding the compatibility of the
project with existing and planned land uses. The PSS’s unsupported
preliminary assessment and planned program of study only adds to the Task
Force’s profound anxiety over the siting of a major new generating
facility in New York City’s most vital and rapidly developing waterfront
community. Moreover, the scope of the project, as
well as the definition of key project parameters, is unacceptably
ambiguous. Major
uncertainties surround such project assumptions as: The
potential for steam sales to Con Edison.
The Applicant must expeditiously resolve whether this is a
realistic possibility or mere wishful thinking. If the former, it is
incumbent upon TransGas Energy to analyze the environmental impacts of the
necessary steam connection buried in the East River between Brooklyn and
Manhattan and other reasonably related structures, as well as a program to
mitigate expected environmental impacts. If the latter, the purported environmental benefits of steam
sales should be dismissed as remote speculative and uncertain. TGE
Response: The
PSS states that the Application will analyze the environmental impacts of
structures related to the steam interconnection. Studies providing for the analysis of interconnections are
included throughout the proposed stipulations. The
reuse of non-potable water by treating the wastewater
effluent from the Newton Creek Water Pollution Control plant. Again, TransGas Energy has provided scant information for
this to be taken as a serious option.
Unless and until this option is integrated into the design of the
plant the Commission should disregard any claimed environmental advantage. Interconnection
to transmission system, gas pipelines and other off-site impacts.
The PSS fails to fully detail and sufficient of environmental
impacts associated with the delivery of natural gas or reinforcement of
the transmission network that will result from this project. TGE
Response: The
PSS cannot detail these impacts because they are not yet known.
This presentation will be made in the Application. Backup
fuel.
The PSS is completely non-committal regarding the use of, and air
quality impacts, associated with backup fuel oil. TGE
Response: TGE
disagrees with this assertion. It
goes without saying that the air quality impacts will be evaluated on both
the primary and backup fuel. Oil
will be used as a back-up fuel. A
primary advantage of the site and a reason for its need to be at this
waterfront location is the existing on-site oil pipeline and
infrastructure to barge supplemental oil to the site. Cumulative
impacts. The applicant fails to address the
need for fair share based upon area's existing footprint for permitted and
planned generation facilities and numerous other municipal and state
permitted uses. TGE
Response: The
applicability of the “Fair Share” criteria to the proposed facility
will be addressed in the Application. Further, as pointed out in the
following sections, the PSS and supporting stipulations do not comport
with the program of studies directed in more recent Article X filings. In particular, the proposed analyses for air quality, land
use, socio-economics, aesthetics and visual resources and noise fail to
reflect the latest Commission thinking on the state of the art in
environmental impact review. TGE
Response: The
comment is not specific enough to formulate a response. Finally, the Task Force regards the
specification of the “no action” alternative and its juxtaposition to
the proposed project as critical to this proceeding. This analysis should, address, with significant input from
community stakeholders, the possible future development of the site and
surrounding area if the Siting Board rejects the proposed facility.
The study must include local land use, environmental and
socio-economic implications of the no build scenario should be included.
The Task Force believes that this study will establish that the project is
incompatible with the intended land use for the site. TGE
Response: The
“no action” alternative will be addressed,
in compliance with guidance provided by prior Siting Board Decisions. The Task Force's comments should not be
construed in any way suggesting that it supports or believes in the
viability of TGE's proposed facility. Notwithstanding, the Task Force has
tried to objectively comment on the PSS and the proposed studies in order
to ensure the development of a thorough and accurate record for the Siting
Board's consideration. COMMENTS
ON THE PRELIMINARY SCOPING STUDY (PSS)
Section
1.3 Purpose of this Statement – Page 1-4 As
indicated in the introduction and explained herein, the PSS does not fully
comply with the Siting Board regulations: ·
The
description of the proposed facility is vague and superficial with regards
to the steam sendout and other aspects of the proposal. PSL § 163.1(a),
16 NYCRR § 1000.4(c)(2)(i). ·
TGE
Response: TGE disagrees. The description of the facility provides a brief discussion
on the basis of available information, consistent with the Siting Board
regulations (PSL § 163). ·
The
"environmental setting" of the project has not included off-site
locations impacted by this facility, despite the fact that off-site
actions would be required. PSL § 163.1(a), 16 NYCRR § 1000.4(c)(1). ·
TGE
Response: TGE disagrees. To describe all off-site locations at this time presumes that
all interconnection studies have been completed and all are
interconnection routes are defined. This
is not the case at this time.
The stipulations will dictate the study areas for not only the
plant, but also the interconnections. ·
Significant
issues raised by the public were mischaracterized. 16 NYCRR § 1000.4(c)(2)(vi). ·
TGE
Response: TGE welcomes public involvement,
so that any differences in interpretation can be clarified. The above comment is not specific as to which issues Task
Force believes were mischaracterized. ·
The
proposed analysis of "reasonable alternatives" is inadequate.
PSL § 163(e), 16 NYCRR § 1000.4(c)(2)(v). ·
TGE
Response: The comment is insufficient to
provide a basis for response. ·
The
PSS only discusses potential positive impacts not negative impacts and
does not mention off-site impacts. Neither
the potentially significant adverse impacts identified by the public nor
the environmental setting that would be affected were discussed. PSL §
163.1(b), 16 NYCRR § 1000.4(c)(2)(ii). ·
TGE
Response: TGE disagrees. The PSS discusses potential impacts and benefits.
Nowhere does it propose that the Application exclude negative
impacts. ·
The
discussion of the proposed study program in lacking. PSL § 163.1(c), 16 NYCRR § 1000.4(c)(2)(iii). The
stipulations are incomplete (Appendix B). ·
TGE
Response: This comment is not specific
enough to provide a basis for a response. ·
The
discussion of measures proposed to minimize environmental impacts and
"an initial identification of mitigation measures" is missing
for several aspects of the project. PSL § 163.1(d), 16 NYCRR §
1000.4(c)(2)(ii). ·
TGE
Response: TGE disagrees, and addresses each
such topic below. PSS SECTION 2.0
- PROJECT DESCRIPTION Section 2.2.1 The Site - Page 2-1
The Applicant proposes to place a large
generating facility on a nine acre site.
Artists illustrations show that the completed facility will
practically cover the entire site. It
seems unlikely that the site is large enough. Further, it is inadequate
for off street parking for construction workers or to accommodate the lay
down areas required during construction. TGE
Response: The
proposed Project is in fact highly land-efficient, even for an urban area.
TGE will present its laydown area and parking plans in the
Application and show how the Project fits on the site. The application should show the
location of all primary and ancillary facilities, off site lay down areas
and off site parking and should discuss the noise and traffic impacts of
these off site facilities. The
Task Force will propose modifications to the noise and transportation
stipulations to reflect these comments. TGE
Response: The
Application will discuss all relevant environmental impacts for all
interconnections. The
PSS presents the site as part of a waterfront dominated by industrial,
manufacturing, and infrastructure uses. This is inaccurate. The closest
active industrial or manufacturing use is the NYPA plant and Domino Sugar
some 8 blocks to the south. The
site immediately to the south of the proposed site is a document storage
facility, (not manufacturing), and directly below that a DOS garbage truck
facility already scheduled to be moved.
Directly to the south of these facilities are four blocks of
waterfront property that NYS and NYU have begun to redevelop into athletic
fields. The NY 2012 Olympic Organizing Committee has slated this site for
volleyball and archery competitions The USA Waste owns the only remaining
property to the south, which is currently on the market for sale.
To the north is the Bushwick Creek Inlet a waterfront area proposed
for open space acquisition by NYS. Directly across the Bushwick Creek
Inlet are several small properties consisting of mainly warehouse
facilities, and the Chimento Trucking property, (owned by the City of New
York), recommended in the Greenpoint 197a plan to become a museum
commemorating the site of the construction and launching of the Civil War
Ironclad Monitor ("Monitor Site") and a public park.
North of that is a large four-block parcel that has been purchased
by a residential developer. The nearest active manufacturing or industrial
use lies beyond a two-block waterfront parcel owned by the NYC Department
of Parks and Recreation. TGE
Response: The Task Force’s description of nearby properties will be
considered during the preparation of the Application pursuant to 16 NYCRR
Part 1001.3(b)(1)(i). The
Application will study the compatibility of the Project and
interconnections with all existing and all approved proposed land uses. The
PSS also incorrectly states that the site “is in a portion of the
waterfront that is as distant from primarily residential blocks of both
Greenpoint and Williamsburg as the East River waterfront allows -
approximately 1,000 feet in all directions.” There is active residential
occupation in buildings as close as 30 feet from the site, (the NE corner
of North 13th Street), another 350 feet from the site, (the SE corner of
North 11th street), and several blocks of live/work lofts 500 feet from
the site (From North 12th street south past North 9th). These situation is
considered by the City as Non-Conforming Use residences, but some are
covered by the NYC Loft Law, even though the zoning is M-1 or Mixed Use.2 TGE
Response: Nothing in the Task Force comment
changes the accuracy of TGE’s statement that the site “is in a portion
of the waterfront that is as distant from primarily residential blocks of
both Greenpoint and Williamsburg as the East River waterfront allows -
approximately 1,000 feet in all directions.”
The sentence spoke of primarily residential blocks, not
non-residential blocks with certain residential uses. It
is the Task Force’s contention the proposed project will halt the
mixed-use development of this large area of the North Brooklyn Waterfront
and become a city wide visible symbol associating negative connotation for
the Greenpoint/Williamsburg Communities. TGE
Response: TGE intends to demonstrate in its
Application that the Project can be designed to be compatible with the
surrounding area, and furthermore can have a positive rather than a
negative connotation for the blocks that immediately surround it.
See Section 10 of the PSS. Section
2.2.2 The Greenpoint and Williamsburg Communities – Page 2-3 The
PSS characterizes the Greenpoint-Williamsburg (“GP/W”) neighborhoods
as a mix of industrial and residential uses. This is not exact as it
ignores light manufacturing established in the area around the site.
Indeed, local plans indicate heavy industrial facilities are inappropriate
for this site. There is
tremendous pressure to increase the housing supply and related support
businesses, as well as open space and parklands. TGE
Response: The Application will address
local plans and will include a discussion responsive to this comment. For
these reasons, Community Board One’s recommended plans for Greenpoint
and Williamsburg ("197-a plans") place priorities upon
increasing affordable low-rise housing stock, waterfront access for
residents, and environmental quality. The Greenpoint 197a plan also calls
for new market rate housing, north of this site at the Greenpoint Terminal
Market site. This site, already purchased by a residential developer, will
become less desirable for market rate housing with the proposed power
plant clearly visible to the south. TGE
Response: TGE understands the proposed
priorities of the subject 197-a plans, but disagrees with the latter
opinion about market rate housing. Very
high real estate prices and rents are possible immediately adjacent to
power plants – for example, the blocks surrounding Waterside, East 74th
Street, and West 59th Street stations in Manhattan. It
seems highly unlikely the application would be able to demonstrate
consistency with City regulations, performance standards and the City, the
Borough and community planning documents. Moreover, the Borough, the
Community Board and elected representatives throughout the area have
expressed their opposition to this project. Section
2.3.4 Water and Wastewater – Page 2-8 Wastewater
flows presents a problem for TGE’s proposal in this site. Wastewater
flows would be discharged into the site's existing sewer connection or by
a separate line to the Newtown Creek WPCP. In page 2-8 TGE states that the
site is presently connected to the sewer system and the alternative to
building a new sewer is not being explored.
These communities are already subject to serious flooding problems. Any increase in wastewater discharged into the sewer system
adds to this problem. This problem needs to be addressed.
Wastewater flows generated by the Project of 500,000 gallons per
day should also be studied in the context of the several thousands of new
housing units that will be added to the GP/W communities in the coming
years by the conversion of existing manufacturing buildings to residential
and the proposed developments at the GTM and Greenpoint Lumber Exchange
sites. The stipulation should reflect this concern. TGE
Response: TGE will evaluate the
requirements of the City of New York for connection to the sewer system in
the Application.
The
Task Force proposes a new stipulation (Stipulation 13) dealing with these
issues. A safety study should determine if the site offers the proper
conditions for security under the current circumstances. The safety and
emergency response plans for the facility require the input of the GP/W
community. Thus, the new stipulations should take into account concerns of
the U.S. Coast Guard, the NYS Police, the NYC Police Department, GP/W
local authorities and local organizations. TGE should also be required to
study an emergency evacuation plan. In light of the security measures
likely to be required for this facility at this site, the project can no
longer seriously offer waterfront access along North 12th Street. A
generation project at this site simply curtails waterfront access and is
incompatible with State Coastal Management Policies. TGE
Response: The application will show how TGE
will comply with applicable security requirements for this type of
facility. Section
2.3.9 Waste Generation and Disposal - Page 2-10 The
project should include information on the hazardous waste resulting from
the clean up of the site, and how TGE will study the appropriate
management of solid and hazardous waste during construction and operation
of the proposed project. Stipulations should develop how to undertake
these studies. See Section 9.6 of the PSS. TGE
Response: TGE proposes to study the
proposed clean-up of the site and the proposed management of solid and
hazardous waste during construction and operation. Section
2.3.10 Project Operation – Page 2-11 A
generation project at this site would not generate jobs for the community.
The operational labor force is presently estimated to consist of
approximately 40 full-time employees. Any light manufacturing use,
supported by the community in the Williamsburg 197a plan, would generate
far more jobs. This concern has to be reflected in the socio-economic
studies and the “no action” scenario. TGE
Response: Job creation under construction
and operation, including secondary effects, will be studied.
The level of job creation under the “no action” scenario will
also be considered. PSS SECTION 3.0 - ENERGY PLANNING Section 3.1.4 Construction and Operation in the
Public Interest - Page 3-2 TGE states that it will submit the
results of a detailed system production cost analysis but does not state
which model or data base it proposes to use.
The selection of a data base can introduce considerable uncertainty
into the model results not only, as TGE acknowledges, because the future
generating stock is uncertain, but also because potential competitors are
unlikely to reveal anticipated running costs.
TGE should provide, in its application, a complete description and
justification of the data base used in its production cost runs and a full
discussion of the uncertainties inherent in the data bases and model
output. TGE
Response: TGE
believes that complying with Stipulation 4, Clause 5 will be sufficient to
allay these concerns. TGE
will provide in the Application a description and justification of the
model and data base. Section 3.2 No Action Alternative - Page 3-3 A clear and unbiased definition of the
“no action alternative” is a key factor in evaluating the
environmental impacts of a proposed action.
For any given proposed action there are likely to be several ways
to define the no action alternative and alternative definitions may affect
the types of environmental studies and analyses undertaken and thus the
details of the stipulations under consideration. In this section of the PSS, TGE
mentions the “no action alternative” in general without defining a
specific “no action alternative” for the proposed action.
The Task Force requests that TGE provide the parties with a
specific definition of the “no action alternative” that TGE proposes
to use in its application. As indicated earlier, stipulations should be
added to include local land use, environmental and socio-economic
implications of the no build scenario. In fact, most stipulations should
include the "no action alternative". TGE
Response: As
stated above, guidance from prior Siting Board decisions will be used to
formulate the analysis of the no-action alternative. Section 3.3 Cooling Technology Alternatives –
Page 3-3 The Task Force agrees that a comparison
of cooling system alternatives should be included in the application.
However, we disagree with TGE’s proposal to give only
“qualitative consideration” to the potential impacts listed at the
bottom of page 3-3 and the top of page 3-4.
The application should include quantitative comparisons of the
cooling alternatives with regards to land requirements, physical
dimensions, visual plume, water demand and consumptive water losses,
incremental water discharge, thermal discharge, noise, and effect of
project efficiency and derating. Useful quantitative engineering
comparisons specific to this project could be made without detailed design
of the cooling alternatives. The cooling alternatives study submitted by the Applicant in
the Bethlehem Energy Center ("BEC") case is a good example of
the type of analysis that should provide TGE.3
The
proposal incorrectly states several cooling technologies are feasible for
this site. As DEC
Commissioner has indicated a once-through cooling system should not be
considered for a new facility. The
discussion of cooling alternatives should include an analysis of alternate
air cooled condenser designs. Modifying engineering design factors such
as: design temperature; number and size of cells; number, diameter and tip
speed of fans; and, condenser height can, within limits, change both the
performance of the power plant and environmental impacts such as noise,
visual impact, and the amount of the site covered by the cooling system
footprint. TGE should propose a draft stipulation
for review by the parties that details the types of qualitative and
quantitative information on cooling system alternatives that will be
included in the application. The
BEC cooling system study is recommended as a model for this stipulation. TGE
Response: TGE
has eliminated once-through cooling from consideration, and therefore is
willing to eliminate it from the subject stipulation. The BEC stipulation is inapposite to the TGE project because
wet cooling and not dry cooling is proposed in that case. The
fundamental issue is not in doubt – TGE intends to install air cooling,
despite its cost disadvantages. Hence,
the issue will be not one of alternatives, but of optimizing the air
cooling design. Task Force
will be free to ask for specific supplemental information in the
stipulation process or during discovery if a particular aspect of the
cooling system design has not been properly optimized, in its view. Section
3.5.1 Primary Fuel - Page 3-4
The Applicant proposes to use 200,000 DTH of natural gas per day.
See page 5-1. TGE essentially
asserts that adequate supply will be available and does not propose any
specific analysis of availability. However, the Applicant should conduct
an analysis of the availability of such supply for the life of the project
that includes existing and future users, including the increased gas usage
associated with recently certified Article X power plants (e.g., Con
Edison, Keyspan) and other proposed Article X power plants, as well as the
restarted the Hudson Avenue Station, the permitted 79.9 Mw barge plant for
the Brooklyn Navy Yard and New York Power Authority mini-generators and
non-major generating facilities in the area. Stipulations should reflect
studies in the context of diversity, price and reliability. TGE Response:
TGE will comply with prior Siting Board decisions on evaluating
fuel supply. Section
3.5.2 Backup Fuel – Page 3-4 TGE
has not specified the estimated time and consumption of the backup fuel.
These aspects of the project need to be determined prior to undertaking
any environmental impact study. In addition, TGE should evaluate both
types of backup fuel - the currently available 0.05% sulfur oil and the as
yet unavailable 0.005% sulfur oil. The Applicant proposes to use natural
gas and asserts that it will use oil only as a backup fuel. In fact, oil will be used not merely for emergency
circumstances, but for all conditions during which gas is unavailable.
These circumstances could be market-based when the price of gas
exceeds oil during the winter season.
The total emission of pollutants and their air quality impacts are
directly related to fuels that will be used at the proposed facility.
Specifically, because the combustion of oil will produce greater
total pollutants than natural gas, the total amount and period of the use
of oil is critical to an accurate analysis of the impact of the project. The Applicant’s analysis of air
quality impacts should be first premised on TGE specifying the periods
during which oil will be used. Specifically,
TGE should establish what circumstances will be deemed to be interruptible
for the project. The air quality analysis must be based on the maximum
period of oil usage. TGE
Response: Oil
use will be considered in the air quality modeling analysis for the DEC
air permit and will also be discussed in the Article X Application. Section
3.6 Peaking Capability – Page 3-5 Another
undefined issue of the proposal is the “peaking capability”. TGE has
stated in page 3-5 that the project “can also be designed with
additional peaking capacity above its base output.”
Either TGE is proposing peaking capability or it is not. The
decision has an important effect on the scope of the environmental studies
required for this proposal. TGE indicates this feature will be considered in the
application. However, this should be defined at an earlier stage to
develop stipulations on this aspect of the project. See comments to
Section 7.3.1. TGE
Response: TGE will specify what peaking
capability is being proposed, and the studies will be designed
accordingly. PSS SECTION 4.0
- PUBLIC INVOLVEMENT
PROGRAM Section
4.1 Community Involvement Process – Page 4-1 TGE's
plan for involving the community lacks validity in all respects. During
TGE’s pre-application phase the PIP has not adequately engaged key
stakeholders. Earlier contacts with the community have been misleading and
confusing. TGE acknowledges they have stirred up a certain amount of
controversy. The PIP program
has failed to comply with the guidelines circulated by DPS regarding
specific components of the program (stakeholder identification, meetings,
educational materials, media outreach, public notification, etc.). Most
important TGE has demonstrated a total lack of familiarity with New York
City and this area of Brooklyn. GWAPP's Preliminary Report on the Clean
Point Energy, LLC (prior name of the project), Proposal for the Bayside
Site on the East River Waterfront, June 2001, illustrates the Applicant
had information at hand to address the public's input on many of the
issues expected in a PSS but has failed to do so. See footnote 2. TGE
has failed to identify appropriate individuals and organizations for
targeted outreach activities. To date, TGE has not contacted at least half
of the civic organizations within 10 blocks of Kent Avenue. To cite just
some of the groups, TGE has never contacted neither Stop the Barge or
Williamsburg Watch who were both at the Borough President’s meeting in
June, 2001. More importantly, these organizations received a PSS for
comments. The flaws of the PIP are explained in detail in Attachment A.
The Task Force requires monthly updates on the consultation process and
the PIP. This information TGE should be presented in the format used in
Table 4-1. TGE
Response: TGE
has followed DPS guidelines regarding elements of the PIP program, perhaps
not in the manner Task Force would perform a PIP.
TGE wishes to point out again that many people contacted would not
meet with us at first. Furthermore,
it was announced by one of the speakers at the June, 2001 meeting
sponsored by GWAPP that the civic groups that comprise GWAPP did not want
to be contacted individually, but rather through GWAPP leadership or
representation. One of the
advantages of the public involvement program is that it is an evolving
process, not a one shot deal, and we will continue our efforts to adapt
and improve the program. We
will begin contacting members of GWAPP and the Task Force individually –
and, as noted in the PSS and elsewhere, any of these organizations can
contact us, as well, and we will be happy to meet with them.
We
will confer with DPS concerning the Task Forces’ request for monthly
updates on PIP activities. TGE
will be providing DPS staff with monthly reports on PIP activities per DPS
guidance.
There is no requirement,
however, to provide monthly PIP updates to any party other than DPS.
Article
X requires DPS to encourage and facilitate communication between an
applicant and interested or affected persons.
As stated above, we are prepared and willing to communicate about
the concerns Task Force has and how TGE may address them.
TGE
Response to Task Force’s Attachment A: There
appears to be some misunderstandings concerning TGE’s consultation
activities prior to submittal of the PSS.
Our explanations will be better clarified in future documents.
The contacts listed in Table 4-1 were a mixture of preliminary
contacts, informal conversations and lengthier discussions.
Although the table distinguishes telephone contacts and written
correspondence from actual and planned meetings
with stakeholders, a number of the descriptions may not have provided the
necessary detail. For
example, meetings or further actions characterized as “Pending” meant
only that further action had not yet occurred.
In no way did TGE mean to suggest or imply that anyone had
officially agreed to meet, or, that a willingness to meet in the future
was equivalent to support of the project.
We would hope that a willingness to talk meant just that – a
discussion. PSS SECTION 5.0
- FUEL SUPPLY AND DELIVERY Section 5.1.2 Gas Delivery and Section 5.2
Information Requirements and Methodology – Page 5-1 and 5-2 On page 5-1, TGE states that system
reinforcements of the local distribution network are anticipated and that
Key Span is commencing studies to determine what upgrades are required.
On page 5-2, TGE discusses an interconnection study to be
undertaken by Key Span that
will, among other things, address the pipeline route and various on and
off-site facilities required for the delivery of gas or the reinforcement
of the KeySpan system. It is not clear if two separate studies are
intended. In any event, the
studies should address, and the application should report, the
environmental impacts of any pipeline, system upgrades or ancillary
structures or equipment required as a result of the construction and
operation of the proposed facility. TGE Response:
Environmental studies of required off-site facilities will be
included in the Application. PSS SECTION 6.0
- ELECTRIC
TRANSMISSION AND STEAM Section 6.2 Proposed Steam Sendout – Page 6-1 A major topic not adequately discussed
in the PSS is the company’s plan to sell steam to the Con Edison Steam
System. The PSS provides very
little information on the aquatic and water quality impacts of a
cross-river link to the Con Edison system or the on-shore impacts of
construction activities or on-shore facilities at either end of the
crossing. TGE
Response: The
PSS provides a brief discussion based on as much information as is
presently available, consistent with PSL § 163.
The Application will describe the potential environmental impacts
of any cross-river steam interconnection and its associated facilities. In prior Article X cases the Chairman
of the Siting Board has ruled that an Applicant must provide sufficient
information on pipelines or transmission leads that will be constructed as
a result of an Article X facility to include the impacts of the associated
facility in the Siting Boards required findings on the environmental
impacts of the facility. This is true even if the pipeline or transmission
line is subject to other subsequent licensing and review proceedings.
The proposed application cannot be judged complete without a
substantial amount of information on the impacts of the steam line. In addition, the PSS fails to address
how the Applicant's plans interact with Con Edison’s plans for its steam
system. Con Edison intends to
retire its Waterside Steam Plant, enlarge steam generating capacity at the
East River Plant and construct new steam lines north from the East River
plant to reinforce transfer capabilities between parts of its system.
The application should address the following questions: ·
Are the Applicants plan's contingent on
any or all of Con Edison’s plans coming to fruition?
·
Would construction of the cross-river
steam line require Con Edison to increase the size of its planned new
steam connections, or make other changes in its system?
·
Does TGE intend to seek other
industrial or commercial steam hosts in the vicinity of the TransGas site? TGE
Response: The
Application will set forth TGE’s position on these questions. In like manner, the application should
provide information on the environmental impacts of off-site water, fuel
and electric transmission interconnects and on any off site reinforcements
of electric, water or fuel infrastructure that must be undertaken as a
consequence of construction of the TGE facility. The Applicant should propose an
additional stipulation that will detail the environmental studies it will
undertake of the impacts of off-site interconnects and system
improvements. See proposed stipulation 15.
TGE
Response: The
requested analysis of interconnections has been written into the
stipulations, by defining “interconnections” in the preamble and
citing interconnections throughout the proposed stipulations. Section
6.4 Electric and Magnetic Fields – Page 6-2
This area has had problems with EMF’s already, particularly in
South Williamsburg. Thus, the proposal requires a separate study on EMF's
in the whole area pursuant to the PSC's established guidelines.
Stipulation 3 should be redeveloped further to reflect this situation. TGE
Response: This comment provides no detail
supporting the statement about EMF. If
the Task Force has specific information, TGE will review it. As the proposed stipulation states, the analysis will comply
with applicable PSC guidelines. PSS SECTION 7.0
- AIR QUALITY AND
METEOROLOGY Section 7.3.1 National and New York Ambient Air
Quality Standards - Page 7-5 The PSS notes that the members of the
Greenpoint and Williamsburg Communities have frequently raised serious
concern regarding the emission and impact of fine particulates – PM 2.5.
Moreover, the PSS represents that the “Project will minimize its
contribution to the formation of PM 2.5 by minimizing the emission of its
regulated precursors – NOX, SO2 and VOC – as well as through its
combustion of clean natural gas and the reduction in PM and PM-10 that it
accomplishes.” PSS Pg. 2-8. The
PSS also claims that regional reductions in PM 2.5 by its use of NOx and
VOC emission credits. The PSS implies that PM 2.5 is
exclusively is produced from the secondary formation in the atmosphere and
that there is no PM 2.5 emissions from the combustion of natural gas and
oil. In fact, both natural
gas and oil produce PM 2.5 emissions.
Of the total particulates produced from the combustion of natural
gas, the range of PM 2.5 is between 70 and 80 %, of which a portion is
condensable particulates that quickly become solid upon emission from
stacks. It is important to note condensable particulates are merely
particulates that are in the gaseous phase and quickly takes on the solid
form upon being emitted from a stack. This is distinguished from secondary
particulate formation of precursor pollutants (e.g., NOx, VOC), which
results from an atmospheric reaction of precursor pollutants to form
particulates. TGE
Response: The
study of the PM-2.5 that the comment distinguishes (primary, including
condensable particulate matter) will in fact be studied per EPA guidance,
consistent with applicable NYSDEC and Siting Board decisions.* Beyond mere representations, the
Applicant fails to specify the manner in which it will conduct an analysis
to support these representations.
The applicant should perform PM 2.5 analysis that, at a minimum
includes the following: ·
Analysis of PM 2.5 particulates from
the combustion of natural gas and oil, including condensable particulates. ·
TGE
Response: This will be done per EPA guidance and applicable NYSDEC and
Siting Board decisions. ·
Analysis of secondary PM formation
associated with the emission of NOx, VOC and Ammonia slip from the SCR
system. ·
TGE
Response: Particulate formation due to post-combustion processes is
accounted for in the emission rate, in that the analysis will include all
secondary formation that can be accounted for in EPA-specified stack
tests. This is consistent
with EPA guidance. ·
Dispersion and impact analysis of total
PM 2.5 associated with the project. ·
TGE
Response: This will be done per EPA guidance and applicable NYSDEC and
Siting Board decisions. TGE proposed
project will be a major source for hazardous air pollutants
(HAPs) under the Clean Air Act. TGE should conduct an analysis of
control technologies that would achieve HAPs control greater than the
technology through a Case-by-Case MACT analysis. The Applicant should
conduct an analysis of design and operational alternatives to reduce HAPs
emissions from the stack and fugitive emissions.
This analysis should factor technical feasibility, cost and
increase HAPs removal.
TGE
Response: TGE
will include a HAPs analysis per Stipulation 1, Clause 2(d). The cumulative impacts analysis should
include existing sources within 5 miles of the proposed site. In addition, it must include the proposed emissions from
recently certified Article X power plants (e.g., Con Edison, Keyspan) and
other proposed Article X power plants, as well as that from the proposed
restarting of the Hudson Avenue Station, the 79.9 Mw barge permitted for
the Navy Yard, the New York Power Authority mini-generators and the
non-major energy facilities in the area.. TGE
Response: As
stated in Section 16 of the PSS, the analysis will include the proposed
and recently built power plants that satisfy the criteria indicated in the
comment. However, as relates
to other existing sources and Task Force’s proposed 5 mile radius, the
cumulative study will follow NYSDEC Air Guides 26 and 36, as well as
applicable CEQR guidance. The Applicant should conduct an
analysis (e.g., PROMOD) of the potential for displacement of older, less
efficient and more polluting plants by the Project and the local air
quality impacts, during base-load and peak-load conditions.
Such analysis should specify the location of all power plants that
would be displaced and the level of displacement. This analysis should incorporate recent load growth
(e.g.. over the last 10 years), as well as reduced load reduction
associated with recent NYS commitments on load reduction measures. This
analysis should include certified Article X power plants (e.g., Con
Edison, Keyspan) and other proposed Article X power plants, as well as
that from the proposed restarting of the Hudson Avenue Station, the 79.9
Mw barge permitted for the Navy Yard, the New York Power Authority
mini-generators and the non-major energy facilities in the area. TGE
Response: TGE
intends to conduct such a study, and proposes to include recently proposed
and built plants following the criteria included in Stipulation 14,
Clauses 3 through 5. The Applicant should also provide an
analysis of the air emissions during start-up, and the projected number of
start-up events on an annual basis. If
the Applicant expects to operate the CTGs independently, such analysis
should include analysis of the start up of each CTG and projected number
of start-up events for each CTG. TGE
Response: Startup
and shutdown conditions will be incorporated into the air quality
analysis, consistent with EPA guidance. The air quality
issues associated with sources other than combustion sources, including
the discharge of ammonia from storage tank loading/unloading operations,
must be evaluated. This
analysis should consist of an analysis of total ammonia slip associated
with the SCR control technology and impacts of the ammonia in the
atmosphere including secondary particulate formation.
TGE
Response: Ammonia
handling will be described in the Application, and worst-case release
scenarios will be analyzed. Ammonia
slip will be evaluated as part of the non-criteria pollutant study, where
ammonia concentrations will be compared to health-based standards.
Secondary particulate formation within the stack is covered as part
of the particulate emissions analysis, which includes an allowance for
conversion of sulfates to particulates (ammonium salts).
Long-term secondary particulate formation has been discussed in
Section 7.3.1 of the PSS. The Applicant proposes the inclusion of
peaking capability by using duct firing in the HRSG.
Duct firing is highly inefficient and produces significantly more
pollution per energy produced that the base-loading components of the
proposed project. The
Applicant should conduct an analysis
of the air quality impacts (e.g., particulates, VOCs) associated with duct
burners. This analysis should include a comparison of particulate and
VOCs emissions with and without the duct burners based on fuel combustion
and electricity produced. TGE
Response: As stated in Section 3.6 of the PSS, duct burning will be
considered as an alternative. If duct burning is eliminated, it will not
be included in the air permit application or air emissions analysis.
If duct burning is selected, it will be presented.
Section 7.3.4 Air Quality Modeling - Page 7-8 TGE proposes that a single stack
height, based on good engineering practice, be used as the basis for the
air dispersion modeling. Since
stack height affects visual impacts and airline safety as well as
pollutant dispersion, the good engineering practice height may not be the
optimum height for the stack. The Task Force requests that the Applicant
run the models using alternate stack heights to be determined after
consultation with the Task Force and the regulatory staff listed in this
section of the PSS. TGE
Response: TGE
will offer to discuss reasonable and practicable stack heights with the
Task Force, consistent with the preparation schedule of the Application
and the proposed facility. Both
higher than “Good Engineering Practice” (GEP) and lower than GEP stack
heights have been requested at various public meetings.
DEC reminds TGE in its comments that any justification for stack
heights other than GEP must comply with Air Guide 26. We also recommend that the selection of
receptor points be coordinated with the comprehensive analysis of impacts
on neighborhoods and community resources (see our comments on section 9.0) TGE Response: TGE believes this approach can be very helpful in
the development of the record, and appreciates it.
Below is a proposed list of receptor points for which
concentrations will be documented. TGE
asks Task Force’s cooperation in identifying any other receptor points.
|