|
Case
01-F-1276 TransGas
Energy Systems, LLC Task Force Comments on TGE Preliminary Scoping
Statement and Proposed Stipulations, with TransGas Energy Responses INTRODUCTION Pursuant to Article X of the Public
Service Law and implementing regulations, the Community Board One and the
Greenpoint Williamsburg Waterfront Task Force[1],
a coalition of 40 Brooklyn community organizations, (hereinafter
collectively “Task Force”), respectfully submit the following comments
on the Preliminary Scoping Statement (“PSS”) of the proposed 1,100
megawatt (Mw) TransGas Energy generation project for the East River
waterfront. The filing of the PSS triggers the duty
on the part of the Applicant to initiate formal consultation with involved
agencies and the public. PSL
§163 (3),(4). The purpose of the Task Force comments submitted herein is
to put the Applicant and involved agencies on notice as to what the
community regards as the fundamental gaps in TransGas Energy’s
identification of, and program to assess the economic, environmental, and
social issues that arise in connection with the project.
These central issues must be fairly, objectively, and
comprehensively addressed in determining whether the project is in the
public interest. PSL § 168 (2)(e). For the reasons set forth in detail
below, TransGas Energy’s PSS is deeply flawed.
Indeed, the PSS is replete with self-serving, inaccurate,
incomplete and misleading narrative regarding the compatibility of the
project with existing and planned land uses. The PSS’s unsupported
preliminary assessment and planned program of study only adds to the Task
Force’s profound anxiety over the siting of a major new generating
facility in New York City’s most vital and rapidly developing waterfront
community. Moreover, the scope of the project, as
well as the definition of key project parameters, is unacceptably
ambiguous. Major
uncertainties surround such project assumptions as: The
potential for steam sales to Con Edison.
The Applicant must expeditiously resolve whether this is a
realistic possibility or mere wishful thinking. If the former, it is
incumbent upon TransGas Energy to analyze the environmental impacts of the
necessary steam connection buried in the East River between Brooklyn and
Manhattan and other reasonably related structures, as well as a program to
mitigate expected environmental impacts. If the latter, the purported environmental benefits of steam
sales should be dismissed as remote speculative and uncertain. TGE
Response: The
PSS states that the Application will analyze the environmental impacts of
structures related to the steam interconnection. Studies providing for the analysis of interconnections are
included throughout the proposed stipulations. The
reuse of non-potable water by treating the wastewater
effluent from the Newton Creek Water Pollution Control plant. Again, TransGas Energy has provided scant information for
this to be taken as a serious option.
Unless and until this option is integrated into the design of the
plant the Commission should disregard any claimed environmental advantage. Interconnection
to transmission system, gas pipelines and other off-site impacts.
The PSS fails to fully detail and sufficient of environmental
impacts associated with the delivery of natural gas or reinforcement of
the transmission network that will result from this project. TGE
Response: The
PSS cannot detail these impacts because they are not yet known.
This presentation will be made in the Application. Backup
fuel.
The PSS is completely non-committal regarding the use of, and air
quality impacts, associated with backup fuel oil. TGE
Response: TGE
disagrees with this assertion. It
goes without saying that the air quality impacts will be evaluated on both
the primary and backup fuel. Oil
will be used as a back-up fuel. A
primary advantage of the site and a reason for its need to be at this
waterfront location is the existing on-site oil pipeline and
infrastructure to barge supplemental oil to the site. Cumulative
impacts. The applicant fails to address the
need for fair share based upon area's existing footprint for permitted and
planned generation facilities and numerous other municipal and state
permitted uses. TGE
Response: The
applicability of the “Fair Share” criteria to the proposed facility
will be addressed in the Application. Further, as pointed out in the
following sections, the PSS and supporting stipulations do not comport
with the program of studies directed in more recent Article X filings. In particular, the proposed analyses for air quality, land
use, socio-economics, aesthetics and visual resources and noise fail to
reflect the latest Commission thinking on the state of the art in
environmental impact review. TGE
Response: The
comment is not specific enough to formulate a response. Finally, the Task Force regards the
specification of the “no action” alternative and its juxtaposition to
the proposed project as critical to this proceeding. This analysis should, address, with significant input from
community stakeholders, the possible future development of the site and
surrounding area if the Siting Board rejects the proposed facility.
The study must include local land use, environmental and
socio-economic implications of the no build scenario should be included.
The Task Force believes that this study will establish that the project is
incompatible with the intended land use for the site. TGE
Response: The
“no action” alternative will be addressed,
in compliance with guidance provided by prior Siting Board Decisions. The Task Force's comments should not be
construed in any way suggesting that it supports or believes in the
viability of TGE's proposed facility. Notwithstanding, the Task Force has
tried to objectively comment on the PSS and the proposed studies in order
to ensure the development of a thorough and accurate record for the Siting
Board's consideration. COMMENTS
ON THE PRELIMINARY SCOPING STUDY (PSS)
Section
1.3 Purpose of this Statement – Page 1-4 As
indicated in the introduction and explained herein, the PSS does not fully
comply with the Siting Board regulations: ·
The
description of the proposed facility is vague and superficial with regards
to the steam sendout and other aspects of the proposal. PSL § 163.1(a),
16 NYCRR § 1000.4(c)(2)(i). ·
TGE
Response: TGE disagrees. The description of the facility provides a brief discussion
on the basis of available information, consistent with the Siting Board
regulations (PSL § 163). ·
The
"environmental setting" of the project has not included off-site
locations impacted by this facility, despite the fact that off-site
actions would be required. PSL § 163.1(a), 16 NYCRR § 1000.4(c)(1). ·
TGE
Response: TGE disagrees. To describe all off-site locations at this time presumes that
all interconnection studies have been completed and all are
interconnection routes are defined. This
is not the case at this time.
The stipulations will dictate the study areas for not only the
plant, but also the interconnections. ·
Significant
issues raised by the public were mischaracterized. 16 NYCRR § 1000.4(c)(2)(vi). ·
TGE
Response: TGE welcomes public involvement,
so that any differences in interpretation can be clarified. The above comment is not specific as to which issues Task
Force believes were mischaracterized. ·
The
proposed analysis of "reasonable alternatives" is inadequate.
PSL § 163(e), 16 NYCRR § 1000.4(c)(2)(v). ·
TGE
Response: The comment is insufficient to
provide a basis for response. ·
The
PSS only discusses potential positive impacts not negative impacts and
does not mention off-site impacts. Neither
the potentially significant adverse impacts identified by the public nor
the environmental setting that would be affected were discussed. PSL §
163.1(b), 16 NYCRR § 1000.4(c)(2)(ii). ·
TGE
Response: TGE disagrees. The PSS discusses potential impacts and benefits.
Nowhere does it propose that the Application exclude negative
impacts. ·
The
discussion of the proposed study program in lacking. PSL § 163.1(c), 16 NYCRR § 1000.4(c)(2)(iii). The
stipulations are incomplete (Appendix B). ·
TGE
Response: This comment is not specific
enough to provide a basis for a response. ·
The
discussion of measures proposed to minimize environmental impacts and
"an initial identification of mitigation measures" is missing
for several aspects of the project. PSL § 163.1(d), 16 NYCRR §
1000.4(c)(2)(ii). ·
TGE
Response: TGE disagrees, and addresses each
such topic below. PSS SECTION 2.0
- PROJECT DESCRIPTION Section 2.2.1 The Site - Page 2-1
The Applicant proposes to place a large
generating facility on a nine acre site.
Artists illustrations show that the completed facility will
practically cover the entire site. It
seems unlikely that the site is large enough. Further, it is inadequate
for off street parking for construction workers or to accommodate the lay
down areas required during construction. TGE
Response: The
proposed Project is in fact highly land-efficient, even for an urban area.
TGE will present its laydown area and parking plans in the
Application and show how the Project fits on the site. The application should show the
location of all primary and ancillary facilities, off site lay down areas
and off site parking and should discuss the noise and traffic impacts of
these off site facilities. The
Task Force will propose modifications to the noise and transportation
stipulations to reflect these comments. TGE
Response: The
Application will discuss all relevant environmental impacts for all
interconnections. The
PSS presents the site as part of a waterfront dominated by industrial,
manufacturing, and infrastructure uses. This is inaccurate. The closest
active industrial or manufacturing use is the NYPA plant and Domino Sugar
some 8 blocks to the south. The
site immediately to the south of the proposed site is a document storage
facility, (not manufacturing), and directly below that a DOS garbage truck
facility already scheduled to be moved.
Directly to the south of these facilities are four blocks of
waterfront property that NYS and NYU have begun to redevelop into athletic
fields. The NY 2012 Olympic Organizing Committee has slated this site for
volleyball and archery competitions The USA Waste owns the only remaining
property to the south, which is currently on the market for sale.
To the north is the Bushwick Creek Inlet a waterfront area proposed
for open space acquisition by NYS. Directly across the Bushwick Creek
Inlet are several small properties consisting of mainly warehouse
facilities, and the Chimento Trucking property, (owned by the City of New
York), recommended in the Greenpoint 197a plan to become a museum
commemorating the site of the construction and launching of the Civil War
Ironclad Monitor ("Monitor Site") and a public park.
North of that is a large four-block parcel that has been purchased
by a residential developer. The nearest active manufacturing or industrial
use lies beyond a two-block waterfront parcel owned by the NYC Department
of Parks and Recreation. TGE
Response: The Task Force’s description of nearby properties will be
considered during the preparation of the Application pursuant to 16 NYCRR
Part 1001.3(b)(1)(i). The
Application will study the compatibility of the Project and
interconnections with all existing and all approved proposed land uses. The
PSS also incorrectly states that the site “is in a portion of the
waterfront that is as distant from primarily residential blocks of both
Greenpoint and Williamsburg as the East River waterfront allows -
approximately 1,000 feet in all directions.” There is active residential
occupation in buildings as close as 30 feet from the site, (the NE corner
of North 13th Street), another 350 feet from the site, (the SE corner of
North 11th street), and several blocks of live/work lofts 500 feet from
the site (From North 12th street south past North 9th). These situation is
considered by the City as Non-Conforming Use residences, but some are
covered by the NYC Loft Law, even though the zoning is M-1 or Mixed Use.2 TGE
Response: Nothing in the Task Force comment
changes the accuracy of TGE’s statement that the site “is in a portion
of the waterfront that is as distant from primarily residential blocks of
both Greenpoint and Williamsburg as the East River waterfront allows -
approximately 1,000 feet in all directions.”
The sentence spoke of primarily residential blocks, not
non-residential blocks with certain residential uses. It
is the Task Force’s contention the proposed project will halt the
mixed-use development of this large area of the North Brooklyn Waterfront
and become a city wide visible symbol associating negative connotation for
the Greenpoint/Williamsburg Communities. TGE
Response: TGE intends to demonstrate in its
Application that the Project can be designed to be compatible with the
surrounding area, and furthermore can have a positive rather than a
negative connotation for the blocks that immediately surround it.
See Section 10 of the PSS. Section
2.2.2 The Greenpoint and Williamsburg Communities – Page 2-3 The
PSS characterizes the Greenpoint-Williamsburg (“GP/W”) neighborhoods
as a mix of industrial and residential uses. This is not exact as it
ignores light manufacturing established in the area around the site.
Indeed, local plans indicate heavy industrial facilities are inappropriate
for this site. There is
tremendous pressure to increase the housing supply and related support
businesses, as well as open space and parklands. TGE
Response: The Application will address
local plans and will include a discussion responsive to this comment. For
these reasons, Community Board One’s recommended plans for Greenpoint
and Williamsburg ("197-a plans") place priorities upon
increasing affordable low-rise housing stock, waterfront access for
residents, and environmental quality. The Greenpoint 197a plan also calls
for new market rate housing, north of this site at the Greenpoint Terminal
Market site. This site, already purchased by a residential developer, will
become less desirable for market rate housing with the proposed power
plant clearly visible to the south. TGE
Response: TGE understands the proposed
priorities of the subject 197-a plans, but disagrees with the latter
opinion about market rate housing. Very
high real estate prices and rents are possible immediately adjacent to
power plants – for example, the blocks surrounding Waterside, East 74th
Street, and West 59th Street stations in Manhattan. It
seems highly unlikely the application would be able to demonstrate
consistency with City regulations, performance standards and the City, the
Borough and community planning documents. Moreover, the Borough, the
Community Board and elected representatives throughout the area have
expressed their opposition to this project. Section
2.3.4 Water and Wastewater – Page 2-8 Wastewater
flows presents a problem for TGE’s proposal in this site. Wastewater
flows would be discharged into the site's existing sewer connection or by
a separate line to the Newtown Creek WPCP. In page 2-8 TGE states that the
site is presently connected to the sewer system and the alternative to
building a new sewer is not being explored.
These communities are already subject to serious flooding problems. Any increase in wastewater discharged into the sewer system
adds to this problem. This problem needs to be addressed.
Wastewater flows generated by the Project of 500,000 gallons per
day should also be studied in the context of the several thousands of new
housing units that will be added to the GP/W communities in the coming
years by the conversion of existing manufacturing buildings to residential
and the proposed developments at the GTM and Greenpoint Lumber Exchange
sites. The stipulation should reflect this concern. TGE
Response: TGE will evaluate the
requirements of the City of New York for connection to the sewer system in
the Application.
The
Task Force proposes a new stipulation (Stipulation 13) dealing with these
issues. A safety study should determine if the site offers the proper
conditions for security under the current circumstances. The safety and
emergency response plans for the facility require the input of the GP/W
community. Thus, the new stipulations should take into account concerns of
the U.S. Coast Guard, the NYS Police, the NYC Police Department, GP/W
local authorities and local organizations. TGE should also be required to
study an emergency evacuation plan. In light of the security measures
likely to be required for this facility at this site, the project can no
longer seriously offer waterfront access along North 12th Street. A
generation project at this site simply curtails waterfront access and is
incompatible with State Coastal Management Policies. TGE
Response: The application will show how TGE
will comply with applicable security requirements for this type of
facility. Section
2.3.9 Waste Generation and Disposal - Page 2-10 The
project should include information on the hazardous waste resulting from
the clean up of the site, and how TGE will study the appropriate
management of solid and hazardous waste during construction and operation
of the proposed project. Stipulations should develop how to undertake
these studies. See Section 9.6 of the PSS. TGE
Response: TGE proposes to study the
proposed clean-up of the site and the proposed management of solid and
hazardous waste during construction and operation. Section
2.3.10 Project Operation – Page 2-11 A
generation project at this site would not generate jobs for the community.
The operational labor force is presently estimated to consist of
approximately 40 full-time employees. Any light manufacturing use,
supported by the community in the Williamsburg 197a plan, would generate
far more jobs. This concern has to be reflected in the socio-economic
studies and the “no action” scenario. TGE
Response: Job creation under construction
and operation, including secondary effects, will be studied.
The level of job creation under the “no action” scenario will
also be considered. PSS SECTION 3.0 - ENERGY PLANNING Section 3.1.4 Construction and Operation in the
Public Interest - Page 3-2 TGE states that it will submit the
results of a detailed system production cost analysis but does not state
which model or data base it proposes to use.
The selection of a data base can introduce considerable uncertainty
into the model results not only, as TGE acknowledges, because the future
generating stock is uncertain, but also because potential competitors are
unlikely to reveal anticipated running costs.
TGE should provide, in its application, a complete description and
justification of the data base used in its production cost runs and a full
discussion of the uncertainties inherent in the data bases and model
output. TGE
Response: TGE
believes that complying with Stipulation 4, Clause 5 will be sufficient to
allay these concerns. TGE
will provide in the Application a description and justification of the
model and data base. Section 3.2 No Action Alternative - Page 3-3 A clear and unbiased definition of the
“no action alternative” is a key factor in evaluating the
environmental impacts of a proposed action.
For any given proposed action there are likely to be several ways
to define the no action alternative and alternative definitions may affect
the types of environmental studies and analyses undertaken and thus the
details of the stipulations under consideration. In this section of the PSS, TGE
mentions the “no action alternative” in general without defining a
specific “no action alternative” for the proposed action.
The Task Force requests that TGE provide the parties with a
specific definition of the “no action alternative” that TGE proposes
to use in its application. As indicated earlier, stipulations should be
added to include local land use, environmental and socio-economic
implications of the no build scenario. In fact, most stipulations should
include the "no action alternative". TGE
Response: As
stated above, guidance from prior Siting Board decisions will be used to
formulate the analysis of the no-action alternative. Section 3.3 Cooling Technology Alternatives –
Page 3-3 The Task Force agrees that a comparison
of cooling system alternatives should be included in the application.
However, we disagree with TGE’s proposal to give only
“qualitative consideration” to the potential impacts listed at the
bottom of page 3-3 and the top of page 3-4.
The application should include quantitative comparisons of the
cooling alternatives with regards to land requirements, physical
dimensions, visual plume, water demand and consumptive water losses,
incremental water discharge, thermal discharge, noise, and effect of
project efficiency and derating. Useful quantitative engineering
comparisons specific to this project could be made without detailed design
of the cooling alternatives. The cooling alternatives study submitted by the Applicant in
the Bethlehem Energy Center ("BEC") case is a good example of
the type of analysis that should provide TGE.3
The
proposal incorrectly states several cooling technologies are feasible for
this site. As DEC
Commissioner has indicated a once-through cooling system should not be
considered for a new facility. The
discussion of cooling alternatives should include an analysis of alternate
air cooled condenser designs. Modifying engineering design factors such
as: design temperature; number and size of cells; number, diameter and tip
speed of fans; and, condenser height can, within limits, change both the
performance of the power plant and environmental impacts such as noise,
visual impact, and the amount of the site covered by the cooling system
footprint. TGE should propose a draft stipulation
for review by the parties that details the types of qualitative and
quantitative information on cooling system alternatives that will be
included in the application. The
BEC cooling system study is recommended as a model for this stipulation. TGE
Response: TGE
has eliminated once-through cooling from consideration, and therefore is
willing to eliminate it from the subject stipulation. The BEC stipulation is inapposite to the TGE project because
wet cooling and not dry cooling is proposed in that case. The
fundamental issue is not in doubt – TGE intends to install air cooling,
despite its cost disadvantages. Hence,
the issue will be not one of alternatives, but of optimizing the air
cooling design. Task Force
will be free to ask for specific supplemental information in the
stipulation process or during discovery if a particular aspect of the
cooling system design has not been properly optimized, in its view. Section
3.5.1 Primary Fuel - Page 3-4
The Applicant proposes to use 200,000 DTH of natural gas per day.
See page 5-1. TGE essentially
asserts that adequate supply will be available and does not propose any
specific analysis of availability. However, the Applicant should conduct
an analysis of the availability of such supply for the life of the project
that includes existing and future users, including the increased gas usage
associated with recently certified Article X power plants (e.g., Con
Edison, Keyspan) and other proposed Article X power plants, as well as the
restarted the Hudson Avenue Station, the permitted 79.9 Mw barge plant for
the Brooklyn Navy Yard and New York Power Authority mini-generators and
non-major generating facilities in the area. Stipulations should reflect
studies in the context of diversity, price and reliability. TGE Response:
TGE will comply with prior Siting Board decisions on evaluating
fuel supply. Section
3.5.2 Backup Fuel – Page 3-4 TGE
has not specified the estimated time and consumption of the backup fuel.
These aspects of the project need to be determined prior to undertaking
any environmental impact study. In addition, TGE should evaluate both
types of backup fuel - the currently available 0.05% sulfur oil and the as
yet unavailable 0.005% sulfur oil. The Applicant proposes to use natural
gas and asserts that it will use oil only as a backup fuel. In fact, oil will be used not merely for emergency
circumstances, but for all conditions during which gas is unavailable.
These circumstances could be market-based when the price of gas
exceeds oil during the winter season.
The total emission of pollutants and their air quality impacts are
directly related to fuels that will be used at the proposed facility.
Specifically, because the combustion of oil will produce greater
total pollutants than natural gas, the total amount and period of the use
of oil is critical to an accurate analysis of the impact of the project. The Applicant’s analysis of air
quality impacts should be first premised on TGE specifying the periods
during which oil will be used. Specifically,
TGE should establish what circumstances will be deemed to be interruptible
for the project. The air quality analysis must be based on the maximum
period of oil usage. TGE
Response: Oil
use will be considered in the air quality modeling analysis for the DEC
air permit and will also be discussed in the Article X Application. Section
3.6 Peaking Capability – Page 3-5 Another
undefined issue of the proposal is the “peaking capability”. TGE has
stated in page 3-5 that the project “can also be designed with
additional peaking capacity above its base output.”
Either TGE is proposing peaking capability or it is not. The
decision has an important effect on the scope of the environmental studies
required for this proposal. TGE indicates this feature will be considered in the
application. However, this should be defined at an earlier stage to
develop stipulations on this aspect of the project. See comments to
Section 7.3.1. TGE
Response: TGE will specify what peaking
capability is being proposed, and the studies will be designed
accordingly. PSS SECTION 4.0
- PUBLIC INVOLVEMENT
PROGRAM Section
4.1 Community Involvement Process – Page 4-1 TGE's
plan for involving the community lacks validity in all respects. During
TGE’s pre-application phase the PIP has not adequately engaged key
stakeholders. Earlier contacts with the community have been misleading and
confusing. TGE acknowledges they have stirred up a certain amount of
controversy. The PIP program
has failed to comply with the guidelines circulated by DPS regarding
specific components of the program (stakeholder identification, meetings,
educational materials, media outreach, public notification, etc.). Most
important TGE has demonstrated a total lack of familiarity with New York
City and this area of Brooklyn. GWAPP's Preliminary Report on the Clean
Point Energy, LLC (prior name of the project), Proposal for the Bayside
Site on the East River Waterfront, June 2001, illustrates the Applicant
had information at hand to address the public's input on many of the
issues expected in a PSS but has failed to do so. See footnote 2. TGE
has failed to identify appropriate individuals and organizations for
targeted outreach activities. To date, TGE has not contacted at least half
of the civic organizations within 10 blocks of Kent Avenue. To cite just
some of the groups, TGE has never contacted neither Stop the Barge or
Williamsburg Watch who were both at the Borough President’s meeting in
June, 2001. More importantly, these organizations received a PSS for
comments. The flaws of the PIP are explained in detail in Attachment A.
The Task Force requires monthly updates on the consultation process and
the PIP. This information TGE should be presented in the format used in
Table 4-1. TGE
Response: TGE
has followed DPS guidelines regarding elements of the PIP program, perhaps
not in the manner Task Force would perform a PIP.
TGE wishes to point out again that many people contacted would not
meet with us at first. Furthermore,
it was announced by one of the speakers at the June, 2001 meeting
sponsored by GWAPP that the civic groups that comprise GWAPP did not want
to be contacted individually, but rather through GWAPP leadership or
representation. One of the
advantages of the public involvement program is that it is an evolving
process, not a one shot deal, and we will continue our efforts to adapt
and improve the program. We
will begin contacting members of GWAPP and the Task Force individually –
and, as noted in the PSS and elsewhere, any of these organizations can
contact us, as well, and we will be happy to meet with them.
We
will confer with DPS concerning the Task Forces’ request for monthly
updates on PIP activities. TGE
will be providing DPS staff with monthly reports on PIP activities per DPS
guidance.
There is no requirement,
however, to provide monthly PIP updates to any party other than DPS.
Article
X requires DPS to encourage and facilitate communication between an
applicant and interested or affected persons.
As stated above, we are prepared and willing to communicate about
the concerns Task Force has and how TGE may address them.
TGE
Response to Task Force’s Attachment A: There
appears to be some misunderstandings concerning TGE’s consultation
activities prior to submittal of the PSS.
Our explanations will be better clarified in future documents.
The contacts listed in Table 4-1 were a mixture of preliminary
contacts, informal conversations and lengthier discussions.
Although the table distinguishes telephone contacts and written
correspondence from actual and planned meetings
with stakeholders, a number of the descriptions may not have provided the
necessary detail. For
example, meetings or further actions characterized as “Pending” meant
only that further action had not yet occurred.
In no way did TGE mean to suggest or imply that anyone had
officially agreed to meet, or, that a willingness to meet in the future
was equivalent to support of the project.
We would hope that a willingness to talk meant just that – a
discussion. PSS SECTION 5.0
- FUEL SUPPLY AND DELIVERY Section 5.1.2 Gas Delivery and Section 5.2
Information Requirements and Methodology – Page 5-1 and 5-2 On page 5-1, TGE states that system
reinforcements of the local distribution network are anticipated and that
Key Span is commencing studies to determine what upgrades are required.
On page 5-2, TGE discusses an interconnection study to be
undertaken by Key Span that
will, among other things, address the pipeline route and various on and
off-site facilities required for the delivery of gas or the reinforcement
of the KeySpan system. It is not clear if two separate studies are
intended. In any event, the
studies should address, and the application should report, the
environmental impacts of any pipeline, system upgrades or ancillary
structures or equipment required as a result of the construction and
operation of the proposed facility. TGE Response:
Environmental studies of required off-site facilities will be
included in the Application. PSS SECTION 6.0
- ELECTRIC
TRANSMISSION AND STEAM Section 6.2 Proposed Steam Sendout – Page 6-1 A major topic not adequately discussed
in the PSS is the company’s plan to sell steam to the Con Edison Steam
System. The PSS provides very
little information on the aquatic and water quality impacts of a
cross-river link to the Con Edison system or the on-shore impacts of
construction activities or on-shore facilities at either end of the
crossing. TGE
Response: The
PSS provides a brief discussion based on as much information as is
presently available, consistent with PSL § 163.
The Application will describe the potential environmental impacts
of any cross-river steam interconnection and its associated facilities. In prior Article X cases the Chairman
of the Siting Board has ruled that an Applicant must provide sufficient
information on pipelines or transmission leads that will be constructed as
a result of an Article X facility to include the impacts of the associated
facility in the Siting Boards required findings on the environmental
impacts of the facility. This is true even if the pipeline or transmission
line is subject to other subsequent licensing and review proceedings.
The proposed application cannot be judged complete without a
substantial amount of information on the impacts of the steam line. In addition, the PSS fails to address
how the Applicant's plans interact with Con Edison’s plans for its steam
system. Con Edison intends to
retire its Waterside Steam Plant, enlarge steam generating capacity at the
East River Plant and construct new steam lines north from the East River
plant to reinforce transfer capabilities between parts of its system.
The application should address the following questions: ·
Are the Applicants plan's contingent on
any or all of Con Edison’s plans coming to fruition?
·
Would construction of the cross-river
steam line require Con Edison to increase the size of its planned new
steam connections, or make other changes in its system?
·
Does TGE intend to seek other
industrial or commercial steam hosts in the vicinity of the TransGas site? TGE
Response: The
Application will set forth TGE’s position on these questions. In like manner, the application should
provide information on the environmental impacts of off-site water, fuel
and electric transmission interconnects and on any off site reinforcements
of electric, water or fuel infrastructure that must be undertaken as a
consequence of construction of the TGE facility. The Applicant should propose an
additional stipulation that will detail the environmental studies it will
undertake of the impacts of off-site interconnects and system
improvements. See proposed stipulation 15.
TGE
Response: The
requested analysis of interconnections has been written into the
stipulations, by defining “interconnections” in the preamble and
citing interconnections throughout the proposed stipulations. Section
6.4 Electric and Magnetic Fields – Page 6-2
This area has had problems with EMF’s already, particularly in
South Williamsburg. Thus, the proposal requires a separate study on EMF's
in the whole area pursuant to the PSC's established guidelines.
Stipulation 3 should be redeveloped further to reflect this situation. TGE
Response: This comment provides no detail
supporting the statement about EMF. If
the Task Force has specific information, TGE will review it. As the proposed stipulation states, the analysis will comply
with applicable PSC guidelines. PSS SECTION 7.0
- AIR QUALITY AND
METEOROLOGY Section 7.3.1 National and New York Ambient Air
Quality Standards - Page 7-5 The PSS notes that the members of the
Greenpoint and Williamsburg Communities have frequently raised serious
concern regarding the emission and impact of fine particulates – PM 2.5.
Moreover, the PSS represents that the “Project will minimize its
contribution to the formation of PM 2.5 by minimizing the emission of its
regulated precursors – NOX, SO2 and VOC – as well as through its
combustion of clean natural gas and the reduction in PM and PM-10 that it
accomplishes.” PSS Pg. 2-8. The
PSS also claims that regional reductions in PM 2.5 by its use of NOx and
VOC emission credits. The PSS implies that PM 2.5 is
exclusively is produced from the secondary formation in the atmosphere and
that there is no PM 2.5 emissions from the combustion of natural gas and
oil. In fact, both natural
gas and oil produce PM 2.5 emissions.
Of the total particulates produced from the combustion of natural
gas, the range of PM 2.5 is between 70 and 80 %, of which a portion is
condensable particulates that quickly become solid upon emission from
stacks. It is important to note condensable particulates are merely
particulates that are in the gaseous phase and quickly takes on the solid
form upon being emitted from a stack. This is distinguished from secondary
particulate formation of precursor pollutants (e.g., NOx, VOC), which
results from an atmospheric reaction of precursor pollutants to form
particulates. TGE
Response: The
study of the PM-2.5 that the comment distinguishes (primary, including
condensable particulate matter) will in fact be studied per EPA guidance,
consistent with applicable NYSDEC and Siting Board decisions.* Beyond mere representations, the
Applicant fails to specify the manner in which it will conduct an analysis
to support these representations.
The applicant should perform PM 2.5 analysis that, at a minimum
includes the following: ·
Analysis of PM 2.5 particulates from
the combustion of natural gas and oil, including condensable particulates. ·
TGE
Response: This will be done per EPA guidance and applicable NYSDEC and
Siting Board decisions. ·
Analysis of secondary PM formation
associated with the emission of NOx, VOC and Ammonia slip from the SCR
system. ·
TGE
Response: Particulate formation due to post-combustion processes is
accounted for in the emission rate, in that the analysis will include all
secondary formation that can be accounted for in EPA-specified stack
tests. This is consistent
with EPA guidance. ·
Dispersion and impact analysis of total
PM 2.5 associated with the project. ·
TGE
Response: This will be done per EPA guidance and applicable NYSDEC and
Siting Board decisions. TGE proposed
project will be a major source for hazardous air pollutants
(HAPs) under the Clean Air Act. TGE should conduct an analysis of
control technologies that would achieve HAPs control greater than the
technology through a Case-by-Case MACT analysis. The Applicant should
conduct an analysis of design and operational alternatives to reduce HAPs
emissions from the stack and fugitive emissions.
This analysis should factor technical feasibility, cost and
increase HAPs removal.
TGE
Response: TGE
will include a HAPs analysis per Stipulation 1, Clause 2(d). The cumulative impacts analysis should
include existing sources within 5 miles of the proposed site. In addition, it must include the proposed emissions from
recently certified Article X power plants (e.g., Con Edison, Keyspan) and
other proposed Article X power plants, as well as that from the proposed
restarting of the Hudson Avenue Station, the 79.9 Mw barge permitted for
the Navy Yard, the New York Power Authority mini-generators and the
non-major energy facilities in the area.. TGE
Response: As
stated in Section 16 of the PSS, the analysis will include the proposed
and recently built power plants that satisfy the criteria indicated in the
comment. However, as relates
to other existing sources and Task Force’s proposed 5 mile radius, the
cumulative study will follow NYSDEC Air Guides 26 and 36, as well as
applicable CEQR guidance. The Applicant should conduct an
analysis (e.g., PROMOD) of the potential for displacement of older, less
efficient and more polluting plants by the Project and the local air
quality impacts, during base-load and peak-load conditions.
Such analysis should specify the location of all power plants that
would be displaced and the level of displacement. This analysis should incorporate recent load growth
(e.g.. over the last 10 years), as well as reduced load reduction
associated with recent NYS commitments on load reduction measures. This
analysis should include certified Article X power plants (e.g., Con
Edison, Keyspan) and other proposed Article X power plants, as well as
that from the proposed restarting of the Hudson Avenue Station, the 79.9
Mw barge permitted for the Navy Yard, the New York Power Authority
mini-generators and the non-major energy facilities in the area. TGE
Response: TGE
intends to conduct such a study, and proposes to include recently proposed
and built plants following the criteria included in Stipulation 14,
Clauses 3 through 5. The Applicant should also provide an
analysis of the air emissions during start-up, and the projected number of
start-up events on an annual basis. If
the Applicant expects to operate the CTGs independently, such analysis
should include analysis of the start up of each CTG and projected number
of start-up events for each CTG. TGE
Response: Startup
and shutdown conditions will be incorporated into the air quality
analysis, consistent with EPA guidance. The air quality
issues associated with sources other than combustion sources, including
the discharge of ammonia from storage tank loading/unloading operations,
must be evaluated. This
analysis should consist of an analysis of total ammonia slip associated
with the SCR control technology and impacts of the ammonia in the
atmosphere including secondary particulate formation.
TGE
Response: Ammonia
handling will be described in the Application, and worst-case release
scenarios will be analyzed. Ammonia
slip will be evaluated as part of the non-criteria pollutant study, where
ammonia concentrations will be compared to health-based standards.
Secondary particulate formation within the stack is covered as part
of the particulate emissions analysis, which includes an allowance for
conversion of sulfates to particulates (ammonium salts).
Long-term secondary particulate formation has been discussed in
Section 7.3.1 of the PSS. The Applicant proposes the inclusion of
peaking capability by using duct firing in the HRSG.
Duct firing is highly inefficient and produces significantly more
pollution per energy produced that the base-loading components of the
proposed project. The
Applicant should conduct an analysis
of the air quality impacts (e.g., particulates, VOCs) associated with duct
burners. This analysis should include a comparison of particulate and
VOCs emissions with and without the duct burners based on fuel combustion
and electricity produced. TGE
Response: As stated in Section 3.6 of the PSS, duct burning will be
considered as an alternative. If duct burning is eliminated, it will not
be included in the air permit application or air emissions analysis.
If duct burning is selected, it will be presented.
Section 7.3.4 Air Quality Modeling - Page 7-8 TGE proposes that a single stack
height, based on good engineering practice, be used as the basis for the
air dispersion modeling. Since
stack height affects visual impacts and airline safety as well as
pollutant dispersion, the good engineering practice height may not be the
optimum height for the stack. The Task Force requests that the Applicant
run the models using alternate stack heights to be determined after
consultation with the Task Force and the regulatory staff listed in this
section of the PSS. TGE
Response: TGE
will offer to discuss reasonable and practicable stack heights with the
Task Force, consistent with the preparation schedule of the Application
and the proposed facility. Both
higher than “Good Engineering Practice” (GEP) and lower than GEP stack
heights have been requested at various public meetings.
DEC reminds TGE in its comments that any justification for stack
heights other than GEP must comply with Air Guide 26. We also recommend that the selection of
receptor points be coordinated with the comprehensive analysis of impacts
on neighborhoods and community resources (see our comments on section 9.0) TGE Response: TGE believes this approach can be very helpful in
the development of the record, and appreciates it.
Below is a proposed list of receptor points for which
concentrations will be documented. TGE
asks Task Force’s cooperation in identifying any other receptor points.
Section 7.3.5 Environmental Justice – Page 7-8 The EPA allows considerable latitude in
the selection of “Communities of Interest” and “Reference
Communities” for the purposes of environmental justice analysis. The
selection of these communities can affect the outcome of the analysis.
Since the Task Force represents communities near the plant, we
request that TGE must consult with the Task Force on the definition of
these communities before the environmental justice study is undertaken.
These studies should be presented in GIS format. TGE
Response: TGE
will offer to a consult with the Task Force, and will coordinate it with
NYSDEC and other interested parties.
In that consultation, TGE, the Task Force and other parties can
discuss the factors presented below by the Task Force in light of their
consistency, inter alia, with
applicable USEPA guidelines and prior analyses submitted to NYSDEC for
Article X facilities. The environmental justice analysis
should not merely be an analysis of a selected radius surrounding the
project site. Such analysis
will result in missing concentrations of sub-populations of minority and
low-income residents. A
legitimate analysis of environmental justice should be based on the
identification of sub-populations (or pockets) of minority and low-income
residents of Williamsburg and Greenpoint, and their proximity to the
proposed site. At a minimum, an
environmental justice air quality analysis should be conducted that
consists of the following factors: ·
All air emissions
from the plant; ·
All existing air
emissions from other power generating and other municipal and state
permitted facilities in the area; ·
Populations and
sub-populations in the area and
include an analysis of the radius of particulate dispersion (PM 10 and PM
2.5); ·
For such
populations and sub-populations, an analysis of the percentage of minority
and low-income residents; and ·
An analysis of the percentage of the
population and sub-populations that suffers from incidence of asthma based
on NYS Department of Health data and local health departments data, if
available. Section 7.3.12 Stack Plume Visibility – Page 7-11 The stack plume visibility analysis
should specify operating conditions likely to affect plume visibility (for
example: operation of the SCR during oil firing, steam or water injection
for peaking operation), estimate the frequency that the plant will be
operated in each mode and analyze the impact of each relevant mode of
operation on plume size and frequency. In addition, the Applicant should
conduct visual analysis of all steam/vapor plumes from the project,
including from the dry cooling system.
This analysis should include the potential visual impact of
secondary particulate formation associated with ammonia slip. TGE
Response: This
analysis will include different scenarios, accounting for fuel,
temperature and load. Note
that there will be no vapor plumes from the dry cooling system. Separately,
there will be an analysis of visual impact due to regional haze formation.
It has been addressed in Section 7.3.3 of the PSS.
Class I areas (pristine areas with strict limits to protect against
haze) are typically used for a screening level analysis. PSS SECTION 8.0
- ARCHEOLOGICAL &
ARCHITECTURAL Section 8.2.2 Historic or Landmark
Sites within One-Half Mile – Page 8-1 TGE should study the impact
of this project on the “Monitor Site”.
The majority of the original Continental Iron Works shipyard is
still open space. It is currently owned by the City of New York and leased
to a trucking company. There
exists a possibility to recreate the atmosphere and environment on the
“Monitor Site” similar to its original conditions. See comments for
Section 2.1.1. TGE
Response: The
Project’s integration with a potential Monitor museum or similar
facility will be studied. Land
ownership information relevant to this parcel will also be presented. Section 8.3.1 Archeological Reconnaissance Survey
- Page 8-4 The East River and Bushwick Inlet have
a long maritime history. The
Monitor was built across the Inlet from the site.
The Archeological Reconnaissance Survey and the Unanticipated
Discovery Plan should cover underwater portions of the site which might be
disturbed by repair of barge facilities or other construction. TGE
Response: Dredging
and spoil handling/disposal issues will be included in the Application,
and the treatment of any recovered artifacts will also be presented. Section 8.3.2 Architectural Survey – Page 8-4 TGE rightly observes that buildings are
the “fundamental obstruction to views in the study area”. Since buildings are less permanent than terrain, views from
historic buildings could change dramatically in the future.
As discussed in the Task Force’s comments on section 10 - Urban
Design and Visual Impacts, the Applicant should consider the potential
effects of planned land use changes (such as the development of a park at
the East District Terminal Property by the NYS and NYU) on viewsheds. TGE
Response: Consistent
with 16 NYCRR Part 1001.3 (b)(1)(i), TGE will consider approved planned
land use changes. PSS SECTION 9.0
- LAND USE Section 9.1 Introduction – Page 9-1 The Task Force regards this section of
the application as critically important to insuring that issues of concern
to the Williamsburg and Greenpoint communities are adequately addressed.
We have two major concerns about the organization and general
thrust of this section of the PSS, which should be rectified in the
application. ·
The Land Use Section of the PSS does
not adequately reflect the rapidly changing nature of these communities.
The Williamsburg and Greenpoint communities are among the most
rapidly changing communities in the City.
Since the TGE project, if built, will be in place for many years,
it is important to consider how these communities have changed in recent
decades and how, in the absence of the TGE project, they are likely to
develop in the future. The
Land Use Section of the application should describe changes in community
land use, economic base, housing stock, income and demographics over the
last two decades and discusses current trends and likely future changes. ·
TGE
Response: TGE understands the Task Force’s comment. The proposed studies
will assess the proposed facility’s compatibility with nearby land uses,
including, residential, open space and other community uses. The fact that the waterfront today does not have the
shipbuilding operations and marine railways of yesteryear can be
stipulated. TGE’s proposal
has not been and will not be premised on the waterfront that once was, but
on the waterfront that exists today and on existing and approved proposed
land uses, consistent with 16 NYCRR Part 1001.3 (b)(1)(i). ·
The Land Use Section of the PSS does
not adequately reflect the cumulative nature of multiple project impacts
on neighborhoods and important community resources. Individual neighborhoods and community resources (parks,
museums, historic sites, schools, etc.) may experience multiple localized
impacts (noise, traffic increases, visual impacts, localized air quality
impacts, etc.) from the project. To
the extent that these impacts are discussed in separate sections of the
report and to the extent that each section uses different geographic
reference points, the cumulative local impacts of the project are
obscured. ·
TGE
Response: See Section 9.4 of the PSS, which states that the land use
analysis will in fact synthesize the various localized impacts as well as
the consideration of the future viability of the affected land use.
This will assure that cumulative local impacts of the Project are
not obscured. The Task Force recommends that: ·
The Applicant, in consultation with the
Task Force, the DPS and DEC identify specific neighborhoods and community
resources likely to experience multiple localized impacts. ·
TGE
Response: TGE accepts this recommendation.
We look forward to these discussions. ·
The Land Use Section of the application
include a summary of the land use, visual, noise, traffic and air quality
impacts of the project on each of the identified neighborhoods and
community resources. These studies should be presented in GIS format. ·
TGE
Response: TGE accepts this recommendation, as well. Section 9.1.1 Planning Programs - Page 9-1
As discussed above, the Williamsburg
and Greenpoint communities are among the most rapidly changing communities
in the City. It is possible
that some older planning and zoning documents may not reflect recent
developments. It would be
useful if this section of the application included a table showing the
date each cited plan or zoning ordinance was adopted or revised and
indicating what plans or ordinances are in the process of being updated. TGE
Response: TGE
will attempt to include the requested table and information to the extent
it is publicly and readily available. The Applicant should identify any
planned changes in land uses likely to remove visual screening or
otherwise modify the visual impact of the facility.
To that end, the Applicant's land use analysis should be
coordinated with its visual and historic resource analyses. TGE
Response: Approved,
planned changes in land use will be identified. The analyses will be coordinated. The stipulations should
include “The New Waterfront Revitalization Program, A proposed 197a
plan” published by the NYC Department of City Planning and
adopted by the New York City Council in 1999. TGE
Response: This document was included in the originally proposed Stipulation
5, Clause 4(a). Section 9.2.1 Waterfront Access and
Industry – Page 9-2 The proposed “pedestrian
bridge” spanning the mouth of the Bushwick Inlet would be an impediment
to the recreational boating use and marina proposed in both the Greenpoint
and Williamsburg 197a plans. TGE
Response: TGE looks forward to pre-application consultations regarding
waterfront access and uses, including this specific issue.
Waterfront amenities were described in the PSS in a manner intended
to solicit input, and no specific design of these amenities has been
selected. Section 9.2.3 Consistency with Coastal Policies -
Page 9-4 TGE states that “The Project is an
industrial use that is both water-dependent and water-related.” While
this may have been true of an earlier generation of steam electric power
plants, which required large volumes of water for condenser cooling, it is
not true of the facility proposed by TGE.
Since the facility, as proposed would utilize air cooled
condensers, with modest make-up water requirements supplied by the
municipal water system or an alternative on-shore source, there is no need
for the plant to be situated near a large water body.
In addition, as designed, the plant’s primary fuel and secondary
fuels would be delivered by pipeline. Barge access is only a construction
convenience and as a back-up delivery system for the secondary fuel. The
Task Force notes that a number of similar combined cycle plants have been
proposed for construction in New York State at sites that are far removed
from significant water bodies. TGE
Response: The
comment does not identify the plants “far removed from significant water
bodies.” To the contrary,
in New York City no similar combined cycle plants have been proposed far
from water bodies. In fact,
similar combined cycle plants – Oak Point, SCS Astoria, Orion Astoria
Repowering, Poletti Expansion, Ravenswood Cogen, East River Repowering,
and Sunset Energy Fleet -- have been proposed along the East River or
Inner New York Harbor, even though only one of these facilities proposes
to use once-through cooling. The
Application will demonstrate consistency of the Project with Coastal Zone
policies. The stipulations should
also include an analysis of the policies put forth in “The New
Waterfront Revitalization Program, A proposed 197a plan” published by
the NYC Department of City Planning, adopted by the City Council in 1999.
This document further defines “Significant Maritime and
Industrial Areas” ("SMIAs") and encourages new water-dependent
and industrial uses to be located within those SMIAs.
Regarding locating such uses outside SMIAs, section 2.0 reads,
“Outside the SMIAs, determination of the suitability of an area for
working waterfront uses will depend on the compatibility of these uses
with surrounding uses and natural features, and an evaluation of the
area’s long-term best use..” Further, section 2.2 item A includes the
following criteria for new industrial uses outside SMIAs: “Criteria to
determine areas appropriate for working waterfront uses outside the
Significant Maritime and Industrial Areas include: ...adequate and
appropriate buffering from surrounding residents; and existing development
patterns.” From the outset the project is inconsistent with many of the
policies set forth in this plan, such as: ·
Encourage new
water-dependent and industrial uses to be located within Significant
Maritime and Industrial Use Areas: The proposed project is not located
within an SMIA as designated by the New Waterfront Revitalization Program. ·
Outside the SMIAs,
determination of the suitability of an area for working waterfront uses
will depend on the compatibility of these uses with surrounding uses: The
proposed project is not compatible with the surrounding uses of
residential, open space, light industry and recreational uses. ·
TGE
Response: TGE disagrees, for reasons stated in
the PSS and to be developed in the Application. ·
Outside the SMIAs,
determination of the suitability of an area for working waterfront uses
will depend on the compatibility of these uses with the area’s long-term
best use: The proposed project would be incompatible with the area’s
long-term best use which is open space, housing, light industry and
recreation. ·
TGE
Response: TGE disagrees, for reasons stated in
the PSS and to be developed in the Application. ·
Criteria to determine areas
appropriate for working waterfront uses outside the SMIAs include adequate
and appropriate buffering from surrounding residential areas: The project
as planned would provide no buffer from the residential occupancy directly
across the street at N13th Street, little buffering from the property at
N11th, little buffering from planned residential development both 2 blocks
to the north and south, and little from other residential locations to the
north and north-east. ·
TGE
Response: TGE disagrees, for reasons stated in
the PSS and to be developed in the Application. ·
Criteria to determine areas
appropriate for working waterfront uses outside the SMIAs include
compatibility with existing development patterns: The proposed project is
contrary to existing development patterns.
Existing development patterns, witnessed by local and city
sponsored planning studies, zoning variances, zoning remapping and recent
sales of property, include no new heavy manufacturing or heavy industrial
uses. ·
TGE disagrees, for reasons stated in the PSS and to be developed in
the Application. The proposed project is
also incompatible with other coastal policies mentioned in the PSS: ·
Support and facilitate
commercial and residential redevelopment in areas well-suited to such
development: TGE assumes the project would not interfere with commercial
or residential redevelopment and that the site is not proposed for
rezoning. This is not true. The
project will interfere with residential development as, by its very
nature, it will discourage home buyers and renters new to the neighborhood
from moving to the prime sites nearby, such as the GTM site, along with
the related commercial support businesses. The GTM site will offer some
1,200 new residential units. Those units will have a full, direct view of the proposed
project as there are only a few single story buildings between the two
sites. In addition, a large development to the South on Kent Avenue faces
the same problems. The conditions for attracting development to Greenpoint
have been slowly nurtured for a long period of time.
This project would likely halt that development. ·
TGE
Response: TGE believes the Project will be
compatible with existing as well as approved planned uses. The Task Force does not present any credible evidence that
development at the GTM site would likely be halted. Real estate projects routinely occur adjacent to power
plants throughout New York City. Furthermore,
Task Force’s comment makes no reference to the site’s existing use and
future use under the “no action” alternative, which is also a factor
in the analysis. Nonetheless,
the comment will be addressed in the Application. ·
Support water-dependent and
industrial uses in New York City coastal areas that are well-suited to
their continued operation: TGE states that the project is an industrial
use that is both water-dependent and water-related. As indicated earlier,
this is simply untrue. ·
TGE
Response: TGE disagrees for the reasons stated
previously. ·
Promote use of New York
City's waterways for commercial and recreation boating and water-dependent
transportation centers: TGE states the Project does not interfere with
this policy. This is also incorrect. Both the Williamsburg and Greenpoint
197a plans propose recreational boating activities in the Bushwick Creek
Inlet. ·
TGE
Response: TGE invites the Task Force to suggest ways TGE can contribute to
the promotion of commercial and recreational boating. TGE expects that the Application
will demonstrate the Project’s compatibility to the maximum extent
practicable with this policy. ·
Minimize environmental
degradation from solid waste and hazardous substances: TGE states the
project would undertake extensive remediation of existing, recognized
environmental conditions. However, remediation of the site would take
place anyway upon the sale of the property due to the Stipulation between
DEC and Texaco Refining & Marketing Inc. regarding Spill # 9804544
dated July, 1988, pursuant to Section 17-0303 of the Environmental
Conservation Law & Section 176 of Navigation Law. ·
TGE
Response: TGE will present in the Application
the results of its studies and analysis as to what parties are responsible
for what portion of site remediation.
TGE has previously stated its belief that the consent order cited
by the Task Force relates only to groundwater remediation and not soil
removal. ·
Provide public access to
and along New York City's coastal waters: Waterfront access suggested in
the PSS is unlikely for security reasons. The Bushwick Creek Inlet is
being placed on the New York State Open Space Acquisition List and the
Trust For Public Land is working to secure it for use by the public.
North 12th Street is a mapped New York City Street.
Access to the water at the street end is possible without this
project. ·
TGE
Response: TGE expects that the Application will
demonstrate the Project’s compatibility to the maximum extent
practicable with this policy and invites the Task Force to work with TGE
to develop proposals for access at or near the Project site. ·
Protect scenic resources
that contribute to the visual quality of the New York City coastal area:
In this particular case, scenic resources adversely impacted include the
views of and from Manhattan. ·
TGE
Response: TGE expects that the Application will
demonstrate the Project’s compatibility to the maximum extent
practicable with this policy. It
is the intent of TGE to make the Project a visual asset, not a liability. See Section 10 of the PSS. ·
Protect, preserve and
enhance resources significant to the historical, archaeological and
cultural legacy of the New York City coastal area: The proposed project
would have a significant negative affect on a significant historic site of
national significance immediately adjacent to the north the site of the
construction and launch of the Civil War Ironclad Monitor.
When built, the surrounding environs on the direct waterfront were
primarily open-air ship yards. There
are plans underway to designate the original construction yard of the
boat’s builder, Continental Iron Works, (now occupied by the Continental
or “Chimento” Trucking yard), as a National Park Service Site
including a museum and marina. The
overwhelming size of the proposed project, as well as the shadow it will
cast across the original launch site, will forever destroy the character
and scale of the Continental Iron Works site. ·
TGE
Response: TGE disagrees with the Task Force’s
opinion. TGE expects that the
Application will demonstrate the Project’s compatibility to the maximum
extent practicable with this policy.
Compatibility with the potential Monitor site will be studied. Section 9.2.4 Local Waterfront
Revitalization Plans – Page 9-6 TGE incorrectly identifies
there are six waterfront plans for the area surrounding the project. There
are actually 7 plans. The
Applicant should also include an analysis of the policies set forth in
“The New Waterfront Revitalization Program, A proposed 197a plan”
published by the NYC Department of City Planning and adopted by City
Council in 1999. TGE also incorrectly indicates that the Greenpoint 197-a plan
recommends six sub-areas of the neighborhood to be rezoned, but not
including the project site or any abutting parcel. In fact, the Greenpoint
plan makes no recommendations for the project site as it is covered in the
Williamsburg 197a plan
TGE
Response: The New Waterfront Revitalization Program is addressed in Section
9.2.3 and Table 9-1 of the PSS. The
Greenpoint 197a plan was described because it includes parcels immediately
adjacent to the proposed site. Modifications made to the
Williamsburg 197a plan dated January 17, 2001, read in pertinent part as
follows: “Extend Subarea 7
up to N14th Street to include the entire M3-1 district north of the BEDT
site. Rezone blocks occupied primarily by light manufacturing uses to
M-1....” “The industrial
retention principle central to this plan favors high performance light
manufacturing uses that are less burdensome to the growing upland
communities over heavy manufacturing.”
Modifications made on January 26, 2001, read in pertinent part:
“Examine the entire M3 district between N14th street and Broadway
to determine the nature and level of industrial activity in the area.
Rezone, where appropriate, to permit high performance light
manufacturing, contextual medium density residential, medium density
commercial, and mixed use....” TGE
Response: TGE offers to work with Task Force to ensure that the Application
identifies and addresses the latest approved 197-a plans. Moreover, the existing
Bayside Oil Terminal parcel has been considered for rezoning. The New York City Comprehensive Waterfront Plan (NYC DCP
92-97) in Summary of Recommendations for Reach 14 item # 18 recommends an
M-1 buffer Zone to the north of Eastern District Terminal Site as well,
item # 17 recommends an M-1 buffer Zone to the south of the GTM site. TGE
Response: All areas proposed for rezoning (including both buffers around the
facilities mentioned in the comment) are included in Figure 9-1 of the
PSS. The Project site avoids
not only the rezoning proposal but also the buffer area for both the GTM
and the BEDT sites. It
should be noted this plan was prepared 9 years ago, conditions and
assumptions underlying those plans have now changed significantly.
These changes have been clearly reflected in the meetings held with
the Department of City Planning in the review period for the Greenpoint
and Williamsburg 197a plans over the past 12 months.
During those sessions, the Department of City Planning has
consistently encouraged rezoning of the majority of the waterfront to
residential with some mixed use and light manufacturing. TGE also incorrectly states
that the Project site is identified as a waterfront manufacturing zoning
district. Under “Reach 14: Brooklyn Upper Bay: Summary of
Recommendations: Working Waterfront.
The Project site is not listed as one for further or future
maritime industrial use. See also Map A. 14. TGE
Response: TGE disagrees. See Map
5.0 of the Comprehensive Waterfront Plan.
Permissibility of continued existing use is not specified for sites
where no redevelopment has been proposed. Section 9.2.4.2 Plan for the Brooklyn
Waterfront – Page 9-8 TGE relies on the Plan for
the Brooklyn Waterfront, to indicate it does not recommend rezoning the
project site. However, this plan is now 7 years old.
Conditions on the waterfront, most notably the number of industrial
business and jobs cited in the document, have changed radically. Moreover,
the Task Force believes this plan has been supplemented by the Waterfront
Revitalization Program discussed above. TGE
Response: TGE will analyze all applicable approved plans, consistent with
Siting Board regulations cited above. Section 9.3 Open Space and Recreation - Page 9-10
Article X requires an analysis of impacts to recreational areas, as
well as alternative use of the proposed site for recreational uses.
Brooklyn and particularly the communities of Greenpoint and Williamsburg
have one of the lowest ratios of open space in New York State.
The analysis of the project should include the impact of the
project on this inequity and on the specific proposed future open space -
such as those set for the in the Greenpoint and Williamsburg 197-a plans.
The Applicant’s analysis should be limited to existing open
space/recreation areas. Such
analysis should examine the alternative use of the project site for
recreational uses. Separately,
adjacent sites which have the potential for open space and recreational
uses should be analyzed for the decreased open space, recreational and
ecological value due to the proximity to a power plant. This analysis
should include plans by NYS and NYU to construct an athletic/park complex
two blocks to the south of the proposed facility and at the "Monitor
Site". TGE
Response: Our
review indicates that Article X and its regulations do not require an
analysis of an alternative use of the contaminated Bayside Fuel site as a
recreational area. The other
elements of the study proposed by the Task Force are being reviewed and
will be discussed during the stipulation process. Section 9.3.3 Additional Populations - Page 9-11
The study area is too limited. It should be extended to at least
one-mile radius.
TGE Response:
TGE is willing to discuss a larger radius with the Task Force and
interested parties. Section 9.4 Land Use Character and Neighborhood
Character – Page 9-11 As discussed in our comments (above) on
section 9.1 of the PSS, the Applicant should consult with the Task Force,
and DPS and DEC Staff to identify specific neighborhoods and community
resources for focused analysis of multiple project impacts. The one-mile
area is too limited considering off-site impacts and the character of the
community. It should be extended at least two miles. TGE
Response: As stated in a previous response, TGE will offer to consult with
all interested parties regarding the scope of the study radius. Section 9.5.1 New York City Zoning
Resolution – Page 9-12 Based upon the artist
rendering contained in the PSS, the statement regarding the compliance
with the maximum Floor Area Ratio may not be accurate. The project appears
to cover the majority of the site. The total sum of the area of each
enclosed floor may exceed the allowable FAR. TGE
Response: This will be analyzed in detail in the section of the Application
that deals with compliance with local laws. Section 9.7 Decommissioning and Restoration
Because the project site is a contaminated site and the cleanup of
such will likely require an engineering/institutional control, the
Applicant must include the long-term monitoring/maintenance requirements
as part of its financial analysis.
TGE Response:
A protocol responsive to this comment will be included in the
Application. PSS SECTION 10.0
- URBAN DESIGN AND VISUAL RESOURCES Section 10.2 Existing Urban Setting –
Page 10-1
Several of the statements in this section are untrue.
The Keyspan natural gas storage tanks have been demolished.
The Greenpoint Lumber Exchange has ceased operation and is being
sold to a residential developer. The
sugar refinery and nearest oil storage tanks are 8 blocks to the south.
See comments to Section 2.2.1. TGE
Response: TGE notes these comments. TGE
will further assess the existing setting. Based on our review, updates will be made, if necessary. Section 10.3 - Information Requirements and
Methodology - Page 10-1 The PSS does not discuss the
“methodology which will be used to assess potential visual impacts
resulting from the construction and operation of the Project” except by
reference to a CEQR technical manual and a NYS DEC policy memorandum -
neither of which has been provided to the parties.
The summary discussions of these documents in Sections 10.3.1 and
10.3.2 provides no specific information on the type of study which the
Applicant will undertake to assess the visibility of the facility.
For example, the Applicant does not state whether a digital
viewshed simulation will be prepared and if
the Applicant intends plan to fly a balloon or erect a crane at the
proposed stack height to verify the viewshed. TGE should provide to the
parties, for comment, a description of the proposed methodology for
determining the areas from which the facility will be visible.
If a balloon or crane is used for viewshed verification, interested
parties should be notified in advance of the date of the verification. TGE
Response: TGE
has provided such a description in Section 10.3.3, where it states that
computerized perspective renderings will be included. To answer a further question in the comment, because of the
urban setting, use of numerous available landmarks of known height
eliminates the need to conduct a crane demonstration or a balloon
demonstration on the site. To
the degree landmarks are used to verify the accuracy of rendering, such
landmarks will be specified for each such rendering.
Per Task Force request, copies of the CEQR Technical Manual
guidelines and the NYSDEC Visual Resources Policy will be provided under
separate cover. Section 10.3.2 NYSDEC Visual Resources
Policy- Page 10-2 Properties eligible for
listing on the National or State Register of Historic Places should
include the adjacent site of the construction and launching of the Civil
War ironclad “Monitor” TGE
Response: TGE notes the Task Force’s comment and will include the adjacent
site in consultations with historic preservation authorities. Section 10.3.3 Renderings - Page 10-3
As discussed in the Task Force’s
comments on section 7.3.12, the size and frequency of stack plumes may
depend on plant operating mode as well as meteorological conditions. The
renderings should include depictions of the “worst case” plume under
the combination of operating mode and weather most favorable for forming
large and visible plumes. TGE
Response: The
proposed rendering will be discussed during the stipulation process.
TGE notes that creating worst case renderings can be misleading for
a number of reasons, e.g., if the frequency of
the plume is very small or if weather conditions mask the plume.
Nevertheless, we are prepared to discuss it. As discussed in the Task Force’s
comments on Section 9.1, land use, visual impact, noise, air quality and
traffic impact analyses should be coordinated in order to facilitate a
comprehensive analysis of the impacts of the facility on key neighborhoods
and community resources. This information should be presented in GIS
format. The Task Force, and other interested parties, should be consulted
on the selection of locations used for simulated views of the facility to
insure adequate coverage of these neighborhoods and community resources. TGE
Response: TGE
will consult with the Task Force, agencies and other interested parties
and will coordinate the analyses. GIS
format will be used as appropriate. As appropriate (see comments on section
10.4 below) the Applicant should prepare visual simulations showing
facility changes (stack height, cooling system design or location)
intended to mitigate visual impacts. TGE
Response: Additional
views showing mitigation will be provided. Section 10.4 Initial Impact Assessment and
Mitigation - Page 10-3 The plant’s exhaust stacks are likely
to be the most visible part of the plant in distant views, while the
massive air cooled condensers are likely to dominate near field views of
the facility. As discussed in our comments on sections 3.3 and 7.3.4, the
height of the plant, exhaust stacks and the type and design specifics of
the plant’s condenser cooling system could significantly affect a
variety of environmental impacts, including plant visibility.
The application should include a discussion of the potential for
mitigating visual impacts through changes in stack height and cooling
system design. If such
modifications are feasible, and after consultation with the Task Force and
other interested parties, the Applicant should prepare renderings of the
facility showing stack or cooling system modifications designed to
mitigate visual impacts. TGE
Response: TGE
will offer to conduct such a consultation with Task Force and interested
parties during the stipulation process. The visual impact assessment should
include a discussion of night time visual impacts from plant lighting
including stack lighting required by the FAA. TGE
Response: Night-time
lighting impacts will be assessed. As discussed in comments on sections
8.3.2 and 9.2.3, in an urban environment it is likely that some visually
sensitive resources are screened from the site by buildings, rather then
terrain. The Applicant should
assess whether or not views of the facility would be significantly
affected by planned changes in land use (the development of parks at the
Brooklyn East District Terminal and "Monitor Site" for example).
In exceptional cases (where a highly important resource is screened
by a single abandoned building for example), it may be appropriate to
analyze the visual impact of removing the screening structure, even if
there are no current plans to do so. TGE
Response: As
stated above, TGE will assess all existing and approved proposed land
uses, consistent with 16 NYCRR Part 1001.3 (b)(1)(i). TGE asks that Task Force state during the stipulations
process what exceptional cases it has in mind. PSS SECTION 11.0
- NOISE Section 11.3.1. Input Data and Propagation Model -
Page 11-2
The noise analysis should be based on prospective uses in proximity
to site – especially recreational/open space and residential uses
identified in local plans (i.e., the 197-a plans). TGE
Response: TGE
will assess all existing and approved proposed land uses in terms of the
noise environment, consistent with 16 NYCRR Part 1001.3 (b)(1)(i). Section 11.4.1 - Construction Noise – Page 11-3 As discussed in our comments on section
2 of the PSS, the application should identify the location of any off-site
lay down areas. The noise
impacts of activities at off-site lay down areas and parking lots should
be analyzed and presented in the application. TGE
Response: TGE
will prepare a noise modeling protocol, which will address this issue.
See also the response to comment on Stipulation 6, Clause 1, below. Where estimated construction sounds
levels are expected to exceed the existing background sound level by more
that 10 dBA, the Applicant should establish and implement a mitigation
plan to minimize such exceedances. TGE
Response: The
noise protocol will include such an assessment. The Applicant should also analyze noise
mitigation measures during construction, including, the use of muffler
systems on its construction equipment and construction schedules developed
in consultation with the community to minimize noise impacts. TGE
Response: This
will be included in the noise mitigation assessment. Section 11.4.2 - Operation Noise – Page 11-3 ·
Noise levels in different operating
modes - The application should discuss differences in any of noise levels
produced during different operation modes (duct firing, steam injection
for peaking, etc.). ·
TGE
Response: This will be assessed in the noise study. ·
Mitigation - The application should
discuss feasible methods of mitigating operating noise. Since operation of air cooled condenser fans is apt to
produce significant noise impacts, the application should discuss
condenser noise mitigation measures such as changing: the design
temperature of the condensers; the size or number of cells; the location
of the condensers; or, the
size, number or tip speed of fans.
If feasible noise mitigation measures would significantly change
the size or appearance of the
air cooled condensers, the visual impact of such changes should be
discussed in the Visual Resources section of the application. ·
TGE
Response: Noise mitigation for the condensers will be discussed in the
Application. It will be
linked to the visual resources study, as suggested. PSS SECTION 12.0
- SOCIO-ECONOMICS Section 12.2.1 Community - Page 12-1
This section implies that at least part
of the analysis of socio-economic impacts will focus on impacts in
Community District One, rather than the city as a whole.
However, the PSS is very vague as to what specific types of impacts
will be studied at a community, rather than a city-wide, level and what
data and methodologies will be used to assess community level impacts.
Stipulation 7 makes no mention of any socio-economic impact
analysis at the community level. TGE
Response: Community
District One, Greenpoint, and Williamsburg are not providers of municipal
services (e.g., trash
collection, road maintenance, etc.).
Accordingly, impacts to such operations are by necessity addressed
at the level of City government or the appropriate agency or utility. The PSS does speak of a mechanism to direct funds for desired
community goals. The Applicant should conduct a
preliminary assessment of the data and methodologies available for
analyzing the socio-economic impacts of the project on Williamsburg and
Greenpoint and prepare for comment by interested parties a proposal for
community level analysis of socioeconomic impacts. These studies should be
presented in GIS format. Such socio-economic study
should compare the proposed economic benefits with those that would exist
if the property were converted to M-1 “light industrial” uses similar
to others in the area. Study should assume construction of new buildings
to the maximum allowed F.A.R. for an M-1 zone, and assume maximum
occupancy by companies ranging from 5,000 sf to 15,000 sf. This study
should also take into account the socio-economic impacts if the proposed
facility halts proposed residential development in the area. TGE
Response: No reasonable basis has been provided to show that, absent the TGE
Project, Bayside Fuel would disappear.
The Task Force appears to be proposing a “no action” scenario.
This subject is addressed in Section 3 above and will be addressed
in the Application. PSS SECTION 13.0
- TRAFFIC AND
TRANSPORTATION Section 13.2.1 - Data Collection and Analysis –
Page 13-1
This section of the PSS includes a list of seven streets and five
study intersections for which data will be collected and for which impact
analyses will be conducted. However,
the PSS does not include any explanation of why those streets and
intersections were selected for study.
The Applicant should provide the parties with the data and analyses
it used to conclude that these intersections, and only these intersections
should be studied. Parties
should be given an opportunity to review and comment on this material
before the Applicant makes a final selection of study intersections.
TGE Response: TGE provides the requested explanation here.
As with any traffic study, the purpose is to
capture the various routes for vehicles coming to and from the site.
The primary routes are: ·
Long
Island Expressway to Greenpoint Avenue to Franklin Street; ·
McGuinness
Boulevard to Greenpoint Avenue to Franklin Street; ·
McGuniness
Boulevard to Nassau Ave. to North 12th Street; ·
Metropolitan
Avenue to Kent Avenue to North 12th Street; On the basis of these routes, TGE selected major
intersections, deriving the intersections that are proposed.
TGE welcomes comments with respect to the choice of routes as well
as the choice of intersections. PSS SECTION 14.
0 -
SOILS GEOLOGY AND SEISMOLOGY No comments at this time. PSS SECTION 15.0
- WATER RESOURCES No comments at this time. PSS SECTION 16.0
- CUMULATIVE IMPACTS Information to be Used in Cumulative
Impact Study - Page 16-1 As the Task
Force understands this section of the PSS, TGE proposes to analyze the
cumulative impact of its proposed facility, NYPA peaking plants and
proposed power plants for which an Article X application has been
submitted to the Siting Board and certified by the Chairman of the Board
as being complete and in compliance with Article X regulations and any
applicable stipulations. However,
a large number of plants have been proposed under Article X and the status
of these proposals changes frequently. It is unclear how TGE’s proposed
studies would deal with the dynamic nature of Article X.
Does TGE propose to limit the study of cumulative impacts to
Article X cases that have been docketed on the day stipulation 12 is
signed? Conversely, is TGE
proposing to include information filed with the Siting Board the day
before TGE files its application? The Task Force believes that it is
important that the Siting Board be provided with the most current
information available on the cumulative impacts of proposed
generation facilities. We
propose a two step process: TGE should include in its application a
cumulative impact analysis which includes all relevant information which
was publicly available thirty days prior to the submission of its
application on all Article X application which had been filed (whether or
not docketed) within 60 days prior to the filing of the TGE application. TGE
Response: TGE
is prepared to discuss a procedure where all Article X filings that have
received compliance determinations no later than sixty days before the
filing of TGE’s Article X Application will be included in the cumulative
impact study. Speculative
projects would bias the analysis. TGE should commit to preparing a
supplement to the cumulative impact analysis which will update cumulative
analysis to reflect developments in other Article X cases. The date for
submittal of the supplement should be set by the presiding examiner at the
time a hearing schedule is established. Thus, this important aspect of the
stipulations should be developed further. This information should be
presented in GIS format. TGE
Response: TGE
believes that cumulative analyses should cover preceding facilities.
If any subsequent facilities are proposed, the proper forum for
addressing cumulative impacts is the application of such a subsequent
facility, just as it is incumbent upon TGE to assess cumulative impacts of
its predecessor facilities. The Task Force notes that in 1991, DEC declared
Greenpoint/Williamsburg the most polluted community district [4.8 sq
miles] in the United States. Because of this they established an
Environmental Benefits Fund Project to fight the existing burdens, and to
gather City, State and Federal data to aid in changing the community. DEC
& DEP were clear sponsors and facilitators of this project. TGE
Response: TGE requests that Task Force
provide the referenced DEC document.
Documentation on the Environmental Benefits Fund Project would also
be appreciated. TGE will
address how the construction and operation of the Project may affect this
issue.
Stipulation No.1 - Air Quality and Meteorology Section 2(e) and 2(h):
As discussed in the Task Force comments on PSS sections 7.3.12 and
10.4, the optimum stack height to mitigate visual and other impacts is
likely to become an issue in this case.
This stipulation should be modified to provide for one or more
additional runs of the dispersion model at alternate stack heights if
necessary to evaluate the air quality impacts of measures proposed to
mitigate visual impacts. The
Task Force envisions that such additional modeling, if necessary, would
take place during the discovery period and after consultation with
interested parties.
TGE Response:
TGE is prepared to discuss the timing, extent and nature of the
analysis to evaluate different stack heights, to the extent consistent
with NYSDEC Air Guide 26.
As discussed in comments on PSS sections 7.3.4, 9.1 and 9.4, the
Task Force believes that it is desirable to coordinate the analysis of
various environmental impacts, including localized concentration of air
pollutants, likely to affect specified neighborhoods and community
resources in Williamsburg and Greenpoint. These neighborhoods and
community resources would be specified after consultation with the Task
Force and other interested parties. The
stipulation should specify that, to the extent practicable, dispersion
modeling results should report impacts at receptor points associated with
these neighborhoods and resources.
TGE Response:
Please see the table, above, that reflects this comment.
Again, TGE believes this approach is very helpful in the
development of the record, and invites Task Force comment on the table. Section 4 - Stack Plume visibility:
The
visibility analysis shall consider the effects of both operating modes and
weather on stack plume visibility.
TGE Response:
TGE agrees with this, and can amend the stipulation accordingly. Stipulation No.2 - Cultural Resources Sections 1 (a) and 3: As
discussed in the Task Force’s comments on PSS section the Archeological
reconnaissance and unexpected discovery plan should include an assessment
of the likelihood of encountering submarine artifacts and a plan for
assessing submarine artifacts if encountered.
TGE Response:
As indicated above, TGE is willing to discuss changing the
stipulation accordingly. Section 4 (c):
As
discussed in the Task Force’s comments on PSS sections 8.3.2
and 10.4 the analysis of impacts should consider the impact of
planned changes in land use on the visibility of the facility from
historic resources, including the "Monitor Site".
TGE Response:
The Application will coordinate its study of approved proposed land
use changes with the visual and cultural resources studies. Stipulation No. 3 - Electric Transmission
Facilities
No Comment at this time. Stipulation No.4 - Project and Fuel Reliability and
Mitigation Alternatives
No Comments at this time. Stipulation No.5 - Land Uses and Local Laws Section 2:
As discussed in the Task Force’s comments on PSS sections 9.1 and
9.4, three new parts should be added to this stipulation: ·
The application to be submitted will
include a description of recent trends in land use, economic base,
demographics and income in the Greenpoint and Williamsburg communities ·
In consultation with the Task Force,
DPS and DEC and other interested parties, the Applicant will identify key
neighborhoods and community resources likely to be affected by multiple
project impacts (traffic, air quality, noise, visual impacts, etc.).
·
For each key neighborhood or community
resource identified, the application to be submitted will include a
summary (based on studies conducted subject to other stipulations) of all
localized project impacts affecting that neighborhood or community
resource. Based on this summary, a
qualitative assessment of the compatibility of the Project with each
specified neighborhood or community resource will be provided.
TGE Response:
As indicated above, TGE will substantively agree to the second and
third proposed paragraph. However,
the first paragraph is not necessary in light of the fact that the land
use study will not be premised
on past uses of the waterfront, but rather on existing and approved
proposed uses (including use of recently published Census data). Section 4:
As
discussed in our comments on section 9.1.1 of the PSS, the application
should include a table showing the date of each plan cited and whether or
not the plan is under revision or scheduled for revision and the
compatibility of the project with those plans.
TGE Response:
TGE will attempt to include the requested table and information to
the extent it is publicly and readily available. Stipulation No.6 - Noise Section 1 - ·
Off-
site lay down areas - As discussed in The Task
Force’s comments on PSS section 11.4.1, this section of the stipulation
should indicate that the location of all off-site lay down areas and
construction parking lots. Subsequent sections of this stipulation should
be modified to include an evaluation of the noise impacts of activities at
off-site lay down areas and parking lots. ·
TGE
Response: Noisy activities
during construction are associated with work that will be conducted
primarily on the Project site. If
noise-producing off-site construction staging areas are proposed in
Greenpoint/Williamsburg area, the specific construction noise will be
assessed. Parking lots are
not a noise source during construction except for brief periods of arrival
and departure, and need not be included in the noise study. ·
Coordination
with Land Use Analysis of Key Neighborhoods and Community Resources. -
As discussed in The Task Force’s comments on PSS section 9.1 and 9.4, it
is desirable to coordinate the evaluation of various project impacts on
key neighborhoods and community resources. This stipulation should be
modified to indicate that all key neighborhoods and community resources
within the area of potential noise impact will be identified on the map
and evaluated as noise receptors. ·
TGE
Response: We will coordinate the noise and neighborhood resource studies
as indicated in the comment. Stipulation No.7 - Socioeconomics
As discussed in the Task Force’s comments on PSS section 12.2.1,
this stipulation should be modified to clearly indicate which
socioeconomic impacts will be studied and reported at a community rather
than a city-wide basis. These studies should be presented in GIS format.
TGE Response:
Based on our response above, TGE does not believe that a change in
the stipulation is necessary, but is prepared to discuss the comment in
more detail with Task Force. Stipulation No.8 - Soils, Geology and Seismology
No comment at this time. Stipulation No.9- Traffic and Transportation Section 2:
As
discussed in the Task Force’s comments on PSS section 13.2.1, the
Applicant has identified seven roadways and five intersections for study
but has not explained how it concluded that these were the appropriate
roadways and intersections for study.
Before finalizing this stipulation, TGE should provide interested
parties with a brief analysis showing why these roadways and
intersections, and no others, should be evaluated in the traffic study.
TGE should consult with the Task Force on the methodology for these
studies.
TGE Response:
TGE’s response has been included above.
TGE looks forward to discussing the issue with Task Force and
interested agencies. Stipulation No.10 - Aesthetics and Visual Resources Section 2(h):
As discussed in the Task Force’s comments on PSS section 10.3.3,
in addition to the proposed analysis of expected warm and cold season
stack plumes, the application should contain an analysis of worst case
stack plumes.
TGE Response:
Worst case stack plumes occur under conditions of high humidity and
cold, for example in snowstorms. To
include such conditions on the background of clear skies would not be
predictive of actual worst-case visual impacts.
It is for this reason that worst-case stack plumes are not
suggested for the visibility analysis. Section 2(i):
As discussed in the Task Force’s comments on PSS section 10.4.3,
the mitigation measures addressed should include lowered stack heights and
as discussed in the Task Force’s comments on PSS section 3.3, reductions
in the height or bulk of the air cooled condensers.
TGE Response:
Downsizing is a mitigation measure included in the NYSDEC Visual
Resources Policy, and as such will be addressed. Section 4(a): ·
Methodology
- As discussed in the Task Force’s comments on PSS section 10.3 this
section of the stipulation should include a much more complete description
of the methodology that TGE will use to prepare and verify the viewshed
map. ·
TGE
Response: TGE will include specifications for the visual simulations. ·
Viewshed
- The Task Force believes that it is
inappropriate to limit the viewshed study area to one mile particularly
given the sites location on the water.
The stipulation should extend the viewshed study area to three
miles. ·
TGE
Response: To be responsive to this comment, TGE proposes to include
viewpoints along the East River and Newtown Creek.
These are the primary areas providing views at distances greater
than 1 mile. Task Force is
also welcome to request additional specific viewpoints for analysis, as
part of the consultation, and TGE will give these viewpoints due
consideration. ·
Coordination
with other studies - As discussed in the Task
Force’s comments on PSS sections 9.1 and 10.3.3 and stipulation 5
section 2, the Task Force believes that it is important to coordinate
those portions of the Applicant’s studies that deal with impacts likely
to affect key neighborhoods and community resources.
The stipulation should state that key neighborhood and community
resources will be shown on the viewshed map and evaluated in the field.
Photographs should be taken from these locations to document existing
views towards the project. ·
TGE
Response: TGE concurs and will consult with Task Force regarding key
neighborhood resources. ·
Planned
Land Use Changes - As discussed in the Task
Force’s comments on PSS section 10.4, the stipulation should commit the
Applicant to reviewing planned land use changes to determine if the
removal of structures currently screening visually sensitive resources is
planned or reasonably foreseeable. If
so, the application should address the impact of such changes on the view
of the facility. ·
TGE
Response: TGE will offer to confer with Task Force and applicable agencies
to determine all approved proposed land uses.
As stated above, if there are specific points which the Task Force
believes are exceptional cases, we would request that they be made
identified by Task Force in pre-application consultations, and their
inclusion in the stipulations can then be discussed. Additional Section to be added to stipulation:
Section 5 of the stipulation implies that the Applicant will
prepare visual simulations. However,
at no point does the stipulation explicitly state that simulations will be
prepared or describe the methodology which will be used to prepare these
simulations. A new section
should be added before section 5 to correct this oversight. TGE Response:
TGE will include specifications for the visual simulations.
As discussed in the Task Force’s comments on PSS section 10.4, in
addition to the simulations prepared for the application, TGE should
commit itself to preparing additional simulations, after consultation with
the parties, if visual mitigation alternatives not currently under
consideration emerge during the Article X proceedings.
TGE Response:
The Parties should attempt to identify reasonable mitigation
alternatives in the Stipulation process.
It is premature to make the requested commitment. Section 5:
The
Task Force should be added to the list of parties consulted about the
selection of visual simulation locations.
TGE Response:
This will be done in a revised Stipulation 11, Clause 5. Stipulation No.11 - Water Resources
The Task Force proposes a new paragraph in the stipulations to
address the impact of the proposed project on the flooding problems in the
area.
TGE Response:
TGE is willing to discuss the issue during stipulation
negotiations. Stipulation No.12 Cumulative Impacts Inconsistency with PSS section 16.0/Quantification
of Impacts:
Paragraph
1 of Stipulation 12 states that (with the exception of air quality,
electric transmission, fuel availability and production modeling studies
detailed in stipulations 1,3 and 4) the study of cumulative impacts will
be “qualitative in character”. However
section 16.0 of the PSS clearly anticipates that some water quality
impacts (consumptive water use and supply and waste water discharge to
municipal treatment plants) will be quantified. This section of the PSS
also implies that cumulative noise and traffic impacts will be quantified.
While not discussed in PSS section 16.0, the Task Force believes
that it would also be feasible and desirable to quantify the cumulative
land use and socioeconomic impacts of multiple projects in the same area.
Stipulation
12 should be modified to indicate that the cumulative impact study will be
“quantitative in all cases where a significant impact can be reasonably
anticipated and where data for a quantitative analysis is available.” TGE Response: TGE
expects to conduct quantitative analysis where feasible, but would not
agree to such language unless Task Force identified, and TGE agreed with,
specific issues where numerical analysis is required, and what specific
tables are required. It is
unreasonable to prescribe quantitative analyses without greater
specificity. Impacts omitted from Consideration:
Paragraph
1 of stipulation 12 includes a list of topics to be considered in the
cumulative impact analysis. The Task Force believes that this list is
incomplete. The Applicant
proposes to limit the analysis of cumulative visual impacts to historic
resources. The Task Force
believes that the study of cumulative visual impacts should be extended to
include other visually sensitive areas identified in Stipulation 10.
The list of topics to be considered in the analysis should be
expanded to include socioeconomic impacts, and the environmental impacts
of gas, electric and steam transmission and ancillary facilities which
must be constructed or upgraded as a result of the construction of
multiple power plants. TGE Response: Task
Force may have misunderstood the intent of the language in paragraph 1.
The only limitation put on the cumulative cultural and visual
resources study is the nature of the cumulative impact (that from power
plants), not the extent of the study area.
The extent of the study area is exactly the same as it will be for
the visual resources study described in Stipulation 10.
With respect to other topics proposed by Task Force, our responses
are as follows: ·
Socioeconomic impacts.
This study was not required in other Article X cases we have
reviewed. ·
Cumulative environmental impacts of interconnection
facilities upgraded due to multiple power plants. The studies that will be conducted by or under the auspices
of Keyspan and Con Edison for system upgrades due to other power plants
presumably will be taken into account in the interconnection studies for
TGE. Additional Stipulations Required Stipulation No.13 - Safety and Protection Systems
As mentioned in the Task Force's comments to the PSS Section 2.3.5.
a new stipulation is required to address if the site offers proper
security conditions for energy generation under the present conditions.
TGE Response:
TGE intends to address security issues and will discuss this during
stipulation negotiations. Stipulation No. 14 - Cooling Technology
Alternatives
As discussed in The Task Force’s comments on PSS section 3.3, TGE
should prepare a stipulation which details that studies it will conduct of
cooling technology alternatives and the material on cooling technology
alternatives to be included in the application.
TGE Response:
See TGE’s response regarding alternative cooling technologies
above. Stipulation No. 15 - Environmental Impacts of
Off-site Interconnects and System Reinforcements
As discussed in The Task Force’s comments on PSS section 6.0, the
Applicant should prepare a stipulation which details the studies it will
undertake of the environmental impacts of the proposed cross river steam
line and of other off-site gas, oil, water, sewer and electric
interconnects and of any off-site reinforcements of the steam, water, gas,
oil, water or sewage systems required as a consequence of the construction
of the proposed facility.
TGE Response: TGE has incorporated all interconnections
into various clauses throughout the stipulations.
No special stipulation is therefore necessary.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| [1]
The Greenpoint-Williamsburg Waterfront Task Force is lead by the
following organizations: Greenpoint Waterfront Association for Parks
and Planning ("GWAPP") and Neighbors Against Garbage
("NAG"). |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 2 A map showing the site and surrounding properties is included in GWAPP's Preliminary Report on the Clean Point Energy, LLC (prior name of the project), Proposal for the Bayside Site on the East River Waterfront, June 2001, at 37. This document has been distributed by GWAPP to the Applicant, the PSC and other interested parties. It is available (without the maps) at http://www.gwapp.org/ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 3
Case 97-F-2162 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| * Memorandum issued October 21, 1997 by John S.
Sietz, Director of the EPA Office of Air Quality Planning and
Standards (MD-10) regarding the interim implementation of new source
review requirements for PM-2.5. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Home Page |